Inspections for the day of: Wednesday, August 17, 2011.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR11-00026 INSP-Final Inspection8/16/20118/17/20118/17/2011 5:02:40 PMPNR
Signals not recieved at central station monitoring. Walkthrough notification testing for the 1st, 2nd and 3rd floors completed acceptable.
BLD11-01344 FIRE-Sprinkler Rough-in8/17/20118/17/20118/17/2011 4:55:58 PMPPART
Six pendent heads at the coffee bar sheetrock ceiling inspected prior to cover.
FIR09-00080 FIR-Aging Inspection8/17/20118/17/20118/17/2011 2:20:42 PM PEND
FIR11-00267 INSP-Final Inspection8/16/20118/17/20118/17/2011 2:16:43 PMAPART
Tested new smoke detection at the 3rd floor east and south towers and 2nd floor central and north floor areas. Reinspected door holders at the 5th floor for functionality after repairs.
BLD11-00761 FIRE-Conference8/16/20118/17/20118/17/2011 2:13:30 PMADONE
Regarding items needed for vanilla permit final including modifications in the existing fire sprinkler system due to remodel work and noted deficiencies.
FIR11-00342 INSP-Sprinkler Rough-in/Hydro8/16/20118/17/20118/17/2011 2:11:08 PMAPART
Okayed overhead rough-in at sheetrock lids adjacent to the restrooms and common corridors.
FIR08-00239 INSP-Sprinkler Rough-in/Hydro8/16/20118/17/20118/17/2011 2:09:13 PMAPART
Overhead hydrostatic test for the 4th floor dry system building #2 passed.