PLM95-00655
| INSP - Water lines | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | | PASS |
|
|
/ / 330 - new service line from tie in to with in 20' of existing buil
|
PLM95-00662
| INSP - Water lines | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | | PART |
|
|
/ / 330 - partial wl ok correction upgrade sprinkler system
|
PLM95-00660
| INSP - Framing/ Rough-in | 8/17/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | A | FAIL |
|
|
08/17/95 330 - waste and vent test failed
|
PLM95-00226
| INSP - Final | 8/17/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | A | PASS |
|
|
08/17/95 330 - final ok 2-wc,3-lav,2-tub,1-si,1-wb,1-wh
|
PLM95-00650
| INSP - Framing/ Rough-in | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | PASS |
|
|
08/18/95 330 - WASTE DRAINAGE REINSPECTION r/i ok
|
PLM95-00651
| INSP - Ground work | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | PASS |
|
|
08/18/95 330 - g/w ok
|
PLM95-00661
| INSP - Sprinkler & Backflow | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | PASS |
|
|
08/18/95 330 -
|
PLM95-00663
| INSP - Sewer line | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | PASS |
|
|
08/18/95 330 - sewer ok
|
PLM95-00663
| INSP - Water lines | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | PASS |
|
|
08/18/95 330 - water ok
|
PLM95-00665
| INSP - Water lines | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | NR |
|
|
08/18/95 330 -
|
PLM95-00665
| INSP - Sewer line | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | NR |
|
|
08/18/95 330 -
|
PLM95-00666
| INSP - Sewer line | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | NR |
|
|
08/18/95 330 -
|
PLM95-00666
| INSP - Water lines | 8/18/1995 | 8/18/1995 | 8/18/1995 12:00:00 AM | P | NR |
|
|
08/18/95 330 -
|