FIR06-00379
| INSP-Sprinkler Rough-in | 8/17/2006 | 8/18/2006 | 8/21/2006 10:21:38 AM | P | PART |
|
|
Inspection for cold cavity protection is satisfactory, OH piping is okay to cover.
|
FIR06-00441
| INSP-Sprinkler Rough-in | 8/17/2006 | 8/18/2006 | 8/18/2006 4:10:19 PM | P | PART |
|
|
Partial inspection for the hard lid areas in the remodeled portion of the project are okay to cover as initialed on the approved plans.
|
BLD06-01589
| FIRE-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 3:25:45 PM | A | FAIL |
|
|
Provide addressing for the second floor, hardware at the boardroom must meet code requirements, 2nd floor only life safety inspection completed today.
|
FIR06-00593
| INSP-Final Inspection | 8/18/2006 | 8/18/2006 | 8/18/2006 2:43:55 PM | P | PASS |
|
|
Hood suppression system functioned properly under test conditions, permit finaled.
|
FIR06-00565
| INSP-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 2:42:23 PM | A | PASS |
|
|
Fire alarm inspection passed.
|
BLD06-01673
| FIRE-Final Inspection | 8/18/2006 | 8/18/2006 | 8/18/2006 1:17:08 PM | P | PASS |
|
|
Fire life safety passed inspection.
|
FIR06-00505
| INSP-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 1:14:13 PM | A | PASS |
|
|
Fire alarm testing is satisfactory, permit finaled.
|
FIR06-00322
| INSP-Sprinkler Rough-in | 8/17/2006 | 8/18/2006 | 8/18/2006 1:13:06 PM | A | PART |
|
|
Rough-in is acceptable at the drop ceiling areas, okay to cover.
|
FIR06-00357
| INSP-Sprinkler Rough-in | 8/17/2006 | 8/18/2006 | 8/18/2006 1:12:26 PM | A | PART |
|
|
OH rough-in is good for cover.
|
FIR06-00355
| INSP-Sprinkler Rough-in | 8/17/2006 | 8/18/2006 | 8/18/2006 1:11:59 PM | A | PART |
|
|
OH rough-in is okay to cover at the drop ceilings.
|
FIR05-00201
| INSP-Sprinkler Rough-in | 8/17/2006 | 8/18/2006 | 8/18/2006 1:11:05 PM | A | FAIL |
|
|
The required minimum separation is not met between upright heads, provide full height wall at the comm. and mech. rooms or extend piping.
|
FIR05-00901
| INSP-Sprinkler Rough-in/Hydro | 8/17/2006 | 8/18/2006 | 8/18/2006 11:49:45 AM | A | PART |
|
|
Overhead hydrostatic test for the three new system zones passed.
|
BLD05-03144
| FIRE-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 10:32:08 AM | A | PASS |
|
|
c/n item is complete, inspection passed.
|
BLD06-01765
| FIRE-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 9:56:20 AM | A | PASS |
|
|
Fire life safety inspection is satisfactory.
|
FIR06-00530
| INSP-Final Inspection | 8/17/2006 | 8/18/2006 | 8/18/2006 9:54:51 AM | A | PASS |
|
|
Final fire sprinkler inspection passed, permit finaled.
|