BLD08-00193
| FIRE-Final Inspection | 8/15/2008 | 8/18/2008 | 8/19/2008 10:12:56 AM | A | PASS |
|
|
life safety passed
|
FIR08-00532
| INSP-Final Inspection | 8/18/2008 | 8/18/2008 | 8/18/2008 4:10:21 PM | P | PASS |
|
|
permit finaled
|
FIR08-00514
| INSP-Sprinkler Rough-in/Hydro | 8/15/2008 | 8/18/2008 | 8/18/2008 3:05:37 PM | A | PASS |
|
|
The underground supply line is ok to bury. The installation matches plans except that a 45 degree elbow as shown on the plans has been deleted with only the 90 elbow turning into the building remaining.
|
FIR08-00434
| INSP-Sprinkler Rough-in | 8/15/2008 | 8/18/2008 | 8/18/2008 3:04:13 PM | A | PASS |
|
|
The underground supply line is ok to bury. The contractor had already buried the thrust block at the in-building riser. I had them dig it out and it appears that it is adequate in size and placement.
|
FIR08-00279
| INSP-Supply line flush | 8/15/2008 | 8/18/2008 | 8/18/2008 1:35:03 PM | A | CANC |
|
|
Need to cancel per Josh Phone #: ###-####
|
FIR08-00526
| INSP-Sprinkler Rough-in | 8/15/2008 | 8/18/2008 | 8/18/2008 1:00:20 PM | A | PART |
|
|
See the city approved plans for locations where the sprinkler piping rough-in passed. Work has been done in the southwest corner of the building which is not shown on the plans. Near this same location are new walls where the sprinkler protection will need to be modified and shown on a set of approved plans. Also the quick responce heads need to be changed to standard responce heads to match the other heads as per bruce and I's conversation.
|