Inspections for the day of: Wednesday, August 18, 2010.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00515 FIR-Aging Inspection8/18/20108/18/20108/19/2010 1:08:16 PM DONE
In progress
FIR07-00817 FIR-Aging Inspection8/18/20108/18/20108/19/2010 1:02:35 PM DONE
Construction suspended.
FIR07-00372 FIR-Aging Inspection8/18/20108/18/20108/19/2010 1:01:25 PM DONE
Construction suspended.
FIR07-00818 FIR-Aging Inspection8/18/20108/18/20108/19/2010 12:58:45 PM DONE
See activity note dated 6/16.
FIR10-00250 INSP-Sprinkler Rough-in8/16/20108/18/20108/18/2010 4:23:01 PMAPART
Preliminary rough-in inspection completed for the two EBeam suites. Resubmittals pending for field modifications in branchline routing.
FIR10-00207 INSP-Final Inspection8/18/20108/18/20108/18/2010 4:18:07 PMPPASS
Fire alarm work completed satisfactory. Permit finaled.
FIR08-00678 INSP-Final Inspection8/17/20108/18/20108/18/2010 4:06:46 PMAPASS
Field inspection passed. Fire alarm permit finaled.
BLD10-01249 FIRE-Conference8/18/20108/18/20108/18/2010 4:05:42 PMADONE
Fire sprinkler system modifications okayed to cover.
BLD10-00123 FIRE-Conference8/18/20108/18/20108/18/2010 4:04:54 PMADONE
Regarding inspection schedule.
FIR10-00372 INSP-Sprinkler Rough-in/Hydro8/18/20108/18/20108/18/2010 4:04:16 PMAPART
Correction items noted at the previous inspection verified for completion- Overhead okayed for cover.
BLD10-01167 FIRE-Final Inspection8/18/20108/18/20108/18/2010 12:00:00 AMPPASS
Andrew Phone #: ###-####