FIR11-00265
| INSP-Sprinkler Rough-in | 8/16/2011 | 8/18/2011 | 8/18/2011 5:52:22 PM | A | CANC |
|
|
Overbooked.
|
FIR11-00281
| INSP-Sprinkler Rough-in | 8/16/2011 | 8/18/2011 | 8/18/2011 5:48:53 PM | A | CANC |
|
|
Overbooked.
|
FIR11-00325
| INSP-Sprinkler Rough-in | 8/16/2011 | 8/18/2011 | 8/18/2011 5:47:43 PM | A | FAIL |
|
|
Riser supervision incorrectly reported as 2nd floor HVAC supervisory. Also noted an inoperable MP station and SD at the riser room.
|
FIR11-00213
| INSP-Sprinkler Rough-in | 8/16/2011 | 8/18/2011 | 8/18/2011 5:40:04 PM | A | PASS |
|
|
Scope of quick permit work passed field inspection. Fire alarm permit finaled.
|
FIR11-00212
| INSP-Final Inspection | 8/15/2011 | 8/18/2011 | 8/18/2011 5:32:27 PM | A | PART |
|
|
Items which remain for final include; provide spare heads at the head box of the type installed, certify the DCVA, re-test alarm and supervisory conditions at the riser. Final walkthrough completed acceptable.
|
FIR11-00211
| INSP-Final Inspection | 8/15/2011 | 8/18/2011 | 8/18/2011 5:23:36 PM | A | PASS |
|
|
Scope of fire sprinkler work passed final walkthrough. Permit finaled.
|
FIR11-00026
| INSP-Final Inspection | 8/17/2011 | 8/18/2011 | 8/18/2011 4:02:58 PM | A | PART |
|
|
Completed testing for ID and DD at the 1st, 2nd, 3rd floor and roof. Noted address changes at two ID on the first floor and the two RTU's AC1 and AC2. IP-DACT per plan has not been installed- phone lines have been provided interm.
|
FIR11-00221
| INSP-Sprinkler Rough-in/Hydro | 8/18/2011 | 8/18/2011 | 8/18/2011 3:56:16 PM | P | PART |
|
|
UG fire supply line hydrostatic test passed.
|
FIR10-00540
| INSP-Final Inspection | 8/17/2011 | 8/18/2011 | 8/18/2011 2:15:42 PM | A | PART |
|
|
|
FIR11-00139
| INSP-Final Inspection | 8/17/2011 | 8/18/2011 | 8/18/2011 2:14:14 PM | A | CANC |
|
|
Overbooked
|
BLD08-01071
| FIRE-Final Inspection | 8/17/2011 | 8/18/2011 | 8/18/2011 2:02:48 PM | A | PART |
|
|
Life safety inspection completed for unit 531. Noted existing fire extinguishers are overdue annual certification by two months.
|
BLD11-01134
| FIRE-Final Inspection | 8/16/2011 | 8/18/2011 | 8/18/2011 1:59:48 PM | A | PASS |
|
|
Reinspection completed acceptable. Verified functional smoke alarms at adjacent apt. units. Life safety passed.
|
FIR11-00391
| INSP-Sprinkler Rough-in/Hydro | 8/18/2011 | 8/18/2011 | 8/18/2011 1:55:33 PM | P | PART |
|
|
Modifications per the scope of work are approved for cover at both the grid and sheetrock ceiling areas.
|
FIR11-00341
| INSP-Sprinkler Rough-in | 8/18/2011 | 8/18/2011 | 8/18/2011 1:52:57 PM | P | PART |
|
|
Overhead rough-in at the new restrooms as marked on approved plan set with today's date are approved for ceiling cover.
|