ESC13-00777
| General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 4:53:17 PM | | PASS |
|
|
Finaled.
|
ESC13-00777
| DOC - Permit Finaled | 8/18/2014 | 8/18/2014 | 8/18/2014 4:49:02 PM | P | PASS |
|
|
Construction activity is complete on the exterior. ESC conditions satisfied.
|
ESC13-00909
| General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 4:32:27 PM | | PART |
|
|
Old parking lot asphalt has been removed. New lot has been graded but is awaiting pavement and landscaping. Some minor trackout to Cassia and sediment in gutter directly in front of work area is present. Need to sweep up after parking lot is paved.
|
ESC13-00213
| General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 4:22:03 PM | | CANC |
|
|
rescheduled for 8/19
|
ESC13-00471
| Aging Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 4:04:04 PM | | FAIL |
|
|
Swales are filled with sediment and debris. There has been no work done by JH development or Sunrise Development as stated. Will reinspect this week to issue corrections to individual SFH projects.
|
ESC13-01279
| Complaint Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 3:50:22 PM | A | FAIL |
|
|
3 corrections required to be completed end of day Tuesday 8/19:
1. Sweep and remove rocks, gravel, and sediment around the intersection of Eckart and Arrow Junction. 2. Empty and replace drop inlet sediment filter bags on all stormdrains around site. 3. Maintain wattles on Eckart south of construction entrance.
|
ESC13-00230
| General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 3:44:10 PM | | PASS |
|
|
RH #5 currently in compliance. No trackout, illicit discharges, or violations observed. BMPs are being maintained.
|
ESC13-00259
| Aging Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 3:31:10 PM | | PASS |
|
|
Triplett Ranch individual townhomes in progress. Hillsides have stabilized/revegetated around the retaining wall. Will keep permit open to check up on temporary BMPs.
|
ESC14-00635
| Site Preparation | 8/18/2014 | 8/18/2014 | 8/18/2014 3:08:17 PM | P | PASS |
|
|
site prep inspection Noah @ 2:00 PM
Met RP Noah onsite. Project is at the rear of the existing building. Stockpiles are to be off-hauled once foundation (slab on grade) is dug, will protect stockpiles if left onsite.
Nearest downstream MS4 DI is on 6th street and Franklin. Sheet flow goes to alley and landscaped area next to project. Permit posted on fence. Construction will begin tomorrow.
|
ESC14-00109
| DOC - Permit Finaled | 8/18/2014 | 8/18/2014 | 8/18/2014 12:58:32 PM | P | PASS |
|
|
ESC permit conditions satisfied. Scope of this project (covering Penitentiary Canal) is complete. Sub development to be covered under ESC14-00788.
|
ESC13-00513
| Aging Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 9:19:03 AM | | PASS |
|
|
|
ESC14-00011
| General Inspection | 8/18/2014 | 8/18/2014 | 8/18/2014 9:04:32 AM | | PASS |
|
|
Finaled.
|
ESC14-00011
| DOC - Permit Finaled | 8/18/2014 | 8/18/2014 | 8/18/2014 9:04:20 AM | P | PASS |
|
|
Project complete. Construction activities and materials no longer at site. ESC conditions satisfied.
|