Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00186 INSP-Alarm Testing8/18/20058/19/20058/19/2005 3:18:43 PMPPART
All that was tested today and passed was the phone lines, battery draw, the smoke detector above the main facp and the interconnection between the fire alarm panel and the NAC panels. What did not pass today was the loss of a/c power was not detected on the stagecoach NAC panel and the NAC panels are not labeled to match the map and the plans. They need to show up on the panel as #1, #2 and #3. Also loss of batteries comes in labeled as a gate valve. These points between the NAC's and the main facp need to be retested to verify that the description/device matches the action. Per the alarm contractor the tamper switch in the pit is off line due to construction of a water line that damaged that part of the circuit.
BLD03-03031 FIRE-Final Inspection8/18/20058/19/20058/19/2005 3:07:45 PMPFAIL
Still need to verify that the sprinkler spacing in the conference room and the additional dry pendants are approved with resubmittals. When the fire sprinkler permit is finaled the life safety can be finaled since items have been checked.
FIR05-00189 INSP-Final Inspection8/19/20058/19/20058/19/2005 3:01:29 PMPPASS
Fire alarm permit finaled
FIR05-00259 INSP-Sprinkler Rough-in/Hydro8/18/20058/19/20058/19/2005 2:06:28 PMPPASS
hydro test for overhead passed
FIR05-00478 INSP-Supply line flush8/18/20058/19/20058/19/2005 12:14:57 PMAPASS
Underground hydro and flush passed.. Piping ok to cover.
BLD05-00347 FIRE-Final Inspection8/19/20058/19/20058/19/2005 11:45:13 AMPPART
A temporary occupancy was given with Jennifer's permission until all items on the correction notice have been corrected.
FIR05-00356 INSP-Final Inspection8/19/20058/19/20058/19/2005 11:44:53 AMPPART
A temporary occupancy was given with Jennifer's permission until all items on the correction notice have been corrected.
BLD05-00236 FIRE-Final Inspection8/19/20058/19/20058/19/2005 10:39:24 AMPCANC
jamal; Phone #: ###-####
BLD05-00979 FIRE-Final Inspection8/18/20058/19/20058/19/2005 9:38:43 AMAPASS
Fire life safety finaled
BLD05-00347 FIRE-Final Inspection8/18/20058/19/20058/19/2005 8:56:21 AMAFAIL
Resubmit building plans showing fencing, gates and storage layout for review of the exiting ussues not previously shown on plans. The warehouse area has racks and storage shelves. The top shelf of the racks is at 10'-10". The top of the storage is at 15'-5" and appears to be encapsulated. The top shelf of the storage shelf's is at 8'-9" with the top of the storage at 10'-5 1/2". The storage for both shelfing systems consists of document boxes. Provide annual inspection for the fire extinguishers, provide documentation that the exit signs and exit discharge lighting can be combined and resubmit fire alarm plans/change map at annunciator.
FIR05-00478 INSP-Final Inspection8/19/20058/19/20058/19/2005 12:00:00 AMPPASS
Fire sprinkler permit finaled. Piping ok to cover.
FIR05-00103 INSP-Final Inspection8/19/20058/19/20058/19/2005 12:00:00 AMPPASS
Permit finaled
FIR05-00217 INSP-Final Inspection8/19/20058/19/20058/19/2005 12:00:00 AMPFAIL
Still need to verify that the sprinkler spacing in the conference room and the additional dry pendants are approved with resubmittals.