FIR13-00339
| INSP-Sprinkler Rough-in | 8/16/2013 | 8/19/2013 | 8/19/2013 8:27:46 PM | P | CANC |
|
|
Rescheduled for tomorrow morning
|
BLD13-01702
| FIRE-Final Inspection | 8/19/2013 | 8/19/2013 | 8/19/2013 3:59:12 PM | P | FAIL |
|
|
Life saafety will be ok to pass when the project related fire alarm permit is finaled.
|
FIR13-00182
| INSP-Alarm Testing | 8/14/2013 | 8/19/2013 | 8/19/2013 3:50:57 PM | A | CANC |
|
|
To be rescheduled per Brian for thursday.
|
FIR13-00391
| INSP-Final Inspection | 8/16/2013 | 8/19/2013 | 8/19/2013 3:47:44 PM | A | FAIL |
|
|
Waiting for map at facp and verification that the lightning suppression is not required.
|
FIR12-00610
| INSP-Sprinkler Rough-in | 8/16/2013 | 8/19/2013 | 8/19/2013 12:38:50 PM | A | PART |
|
|
Piping can be covered but several locations marked in red have upright sprinkler coverage overspaced due to insulation. Also several of the classroom closets have surface mounted light fixtures located right next to sprinkler heads. Ceiling tile will need to be removed to verify these corrections.
|
FIR13-00392
| INSP-Sprinkler Rough-in | 8/16/2013 | 8/19/2013 | 8/19/2013 12:36:26 PM | A | PASS |
|
|
rough to cover passed. Piping is ok to cover.
|