PLM02-02376
| Sprinkler (Final) | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PART |
|
|
peblo ###-#### tie in ok needs testing 8/2/2002 9:24:52 AM
|
PLM02-02375
| Plumbing Rough-in | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/01/2002 at 12:17:48. Contact: ###-####. this is for a gw and it was ok 8/2/2002 10:04:02 AM
|
PLM02-02377
| Water and/or Sewer | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
###-####
|
PLM02-02378
| Water and/or Sewer | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
###-####
|
PLM02-02379
| Plumbing Rough-in | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
NANCY ###-#### ri ok 8/2/2002 10:44:32 AM
|
PLM02-02382
| Plumbing Rough-in | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
GREG ###-####
|
PLM02-02371
| Plumbing Rough-in | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 08/01/2002 at 15:15:12. Contact: .
|
PLM02-01564
| Final | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
TRACEY; Phone #: ###-####
|
PLM02-01245
| Final | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 08/01/2002 at 16:38:13. Contact: ###-####.
|
PLM02-02218
| Water and/or Sewer | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/01/2002 at 17:46:23. Contact: ###-####. this is the test on the gw and below floor waste piping 8/2/2002 9:10:37 AM
|
PLM02-01534
| Final | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 08/02/2002 at 09:07:50. Contact: ###-####. house is ok but a-z sprinkler needs a permit prior to final 8/2/2002 2:44:36 PM
|
PLM02-02395
| Plumbing Rough-in | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM02-02396
| Sprinkler (Final) | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM02-02084
| Plumbing Rough-in | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | NR |
|
|
RAUL ###-#### waste looks ok test was on with a couple of vent leaks, water needs testing, and hangers on the vents 8/2/2002 4:38:55 PM
|
PLM02-01621
| Final | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | PASS |
|
|
|
PLM02-01853
| Final | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | PASS |
|
|
OK PER BILL TO PUT IN FOR THIS AFTERNOON
|
PLM02-02041
| Sprinkler (Final) | 8/2/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | PASS |
|
|
|
PLM02-02170
| Groundwork | 8/1/2002 | 8/2/2002 | 8/2/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 08/01/2002 at 16:14:42. Contact: ###-####. trench drains ok need resubmitted stamped plans 8/2/2002 3:47:07 PM
|