BLD10-01192
| FIRE-Final Inspection | 7/30/2010 | 8/2/2010 | 8/2/2010 3:36:42 PM | A | FAIL |
|
|
Need to get the duct smoke detectors tested and provide exit discharge lighting as discussed.
|
BLD10-01192
| FIRE-Alarm Testing | 7/30/2010 | 8/2/2010 | 8/2/2010 3:26:52 PM | A | FAIL |
|
|
The two duct detectors were not tested because the required remote annunciators had not been provided.
|
FIR10-00231
| INSP-Final Inspection | 8/2/2010 | 8/2/2010 | 8/2/2010 2:44:19 PM | P | FAIL |
|
|
Provide as-built drawings showing the additional fifteen existing duct smoke detectors, test all of the duct smoke detectors, provide verification of code compliant installation of the duct detectors (location & immediate shutdown), provide signage as per the review comment #30, provide map at the facp/annunciator as per review note #28, provide copy of the test signals from today.
|
FIR10-00238
| INSP-Sprinkler Rough-in | 8/2/2010 | 8/2/2010 | 8/2/2010 2:29:10 PM | P | PART |
|
|
Need to remove the smoke curtain/draft stop. Need hydro test. Need the "load splitters" hanger assemblies for the main addressed per tim frost. On closet on the second floor has a ceiling and has not been provided sprinkler protection. Also the sprinkler piping located above the first floor ceiling in the office area needs inspection.
|
FIR10-00262
| INSP-Sprinkler Rough-in | 8/2/2010 | 8/2/2010 | 8/2/2010 2:25:52 PM | P | PASS |
|
|
Todays inspection verified sprinkler deflector distance from the deck, ESFR sprinkler SIN numbers and branchline hangers. Still need to complete the inspection on the riser, hydro tests...ect. Also needed are the main hangers "load splitters" addressed as per tim frost.
|