ELE13-02322
| ELE-Aging Inspection | 8/2/2016 | 8/2/2016 | 8/5/2016 6:46:45 AM | | CANC |
|
|
|
ELE11-00142
| ELE-Aging Inspection | 8/2/2016 | 8/2/2016 | 8/5/2016 6:46:20 AM | | CANC |
|
|
|
ELE16-01838
| Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 3:36:46 PM | P | PASS |
|
|
ceiling inspection Level 8 stack 4, call John. Phone #: ###-#### Inspection requested via web by Brandon Robinson Level 8 stack 3 south and 4 ceiling rough in ok cover.
|
ELE16-00089
| Conference | 8/1/2016 | 8/2/2016 | 8/2/2016 2:53:36 PM | A | DONE |
|
|
Call Rafael to discuss outlets in ceiling area of ballroom. Phone #: ###-#### Inspection requested via web by Rafael Castillo Discussed location of receptacle outlets above a "grid cloud". Flexible cords are not to be installed above grid in any application as per NEC 400.8 uses not permitted. Receptacle outlets shown for temporary equipment for events shall be mounted in or below grid level.
|
ELE15-03901
| Conference | 8/2/2016 | 8/2/2016 | 8/2/2016 11:32:13 AM | P | DONE |
|
|
Sign TCO sheets for 6th and 7th floor that ESI now has set up in a binder as per Dave Hannah''s request. Phone #: ###-#### Inspection requested via web by Rafael Castillo Signed off on floors 6 and 7 in new book provided
|
ELE16-00303
| Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 11:30:51 AM | A | PART |
|
|
TCO inspection. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Floor 2- complete central stair lighting. Framing at main floor entrance, sconce omitted, flourescent under landings not installed may be omitted. Covers missing for card readers on several walls. Cover gutter i electrical room. 3rd floor- Server room fire suppression, HVAC, rack yet to complete. Door shall be lockable and missing window. Card reader boxes at several locations not covered. Room 368 conference table power supply not compatible with floor box provided. location different. Armored cable whip provided and receptacle installed in floor.
|
ELE15-02641
| Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 9:27:03 AM | A | PASS |
|
|
3rd ; 4th Floor Corridor drops Phone #: ###-#### Inspection requested via web by Kerri Hamilton Floor 3, 4, 5, corridor drop hardlids rough in ok cover
|
ELE16-02484
| Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 9:07:35 AM | A | PASS |
|
|
Roberts. Cover Phone #: ###-#### Inspection requested via web by Sean DeLacy Wall rough in ok cover
|
ELE15-02740
| Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 8:44:54 AM | A | PASS |
|
|
Seth Phone #: ###-#### Main lobby and breakfast area grid rough in ok cover
|
ELE15-03901
| Electrical Rough-In | 8/2/2016 | 8/2/2016 | 8/2/2016 7:53:21 AM | P | CANC |
|
|
Call Rafael for pre-walk final of 8th floor. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
|
ELE15-03901
| Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 7:51:03 AM | A | CANC |
|
|
Pre-walk 8th floor to prepare for final inspection of the floor. Review and sign TCO sign-off sheet for 6th anf 7th floors as per Dave Hannah''s request. Call Rafael for inspection. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
|