FIR19-00487
| INSP-Sprinkler Rough-in | 8/20/2019 | 8/20/2019 | 8/20/2019 3:35:10 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Mike Phone #: ###-####
|
FIR19-00168
| INSP-Sprinkler Rough-in | 8/19/2019 | 8/20/2019 | 8/20/2019 2:14:41 PM | P | PART |
|
|
Rough in inspection for dry system addition on top level of parking structure complete.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
FIR18-00678
| INSP-Final Inspection | 8/15/2019 | 8/20/2019 | 8/20/2019 10:57:16 AM | P | PASS |
|
|
Final fire sprinkler inspection for scope of work complete.
Phone #: ###-#### Inspection requested via web by Connie Danes
|
FIR19-00279
| INSP-Final Inspection | 8/15/2019 | 8/20/2019 | 8/20/2019 10:56:51 AM | P | PASS |
|
|
Final fire alarm inspection for scope of work complete.
Ray McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose Peterson
|
BLD19-01338
| FIRE-Final Inspection | 8/19/2019 | 8/20/2019 | 8/20/2019 10:13:30 AM | A | PASS |
|
|
Previously noted item has been corrected, no fire sprinklers, no fire alarms, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.
natalie Phone #: ###-####
|
FIR19-00089
| INSP-Final Inspection | 8/20/2019 | 8/20/2019 | 8/20/2019 9:53:44 AM | P | PASS |
|
|
As builts have been accepted, permit finaled.
As built submitted Phone #: ###-#### Inspection requested via web by Brian Richard
|
NAF18-00133
| INSP-Final | 8/20/2019 | 8/20/2019 | 8/20/2019 9:52:12 AM | A | PART |
|
|
Final underground supply inspection complete.
|
NAF18-00133
| INSP-Supply line flush | 8/19/2019 | 8/20/2019 | 8/20/2019 9:51:14 AM | A | DONE |
|
|
Undergorund main line flush complete.
Please contact Troy Nelson, for a time frame, so we can coordinate with Garden City Water Dept. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
BLD19-01807
| FIRE-Final Inspection | 8/19/2019 | 8/20/2019 | 8/20/2019 9:11:49 AM | A | FAIL |
|
|
Provide fire sprinkler head under new overhead door, a permit is required for fire sprinkler modifications. Provide fire extinguisher with a current inspection tagt.Call 15 to 20 minutes ahead // John Phone #: ###-####
|
FIR19-00180
| INSP-Final Inspection | 8/19/2019 | 8/20/2019 | 8/20/2019 12:00:00 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Jonathan LaFond
|