Inspections for the day of: Tuesday, August 21, 2012.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-00379 BLD-Final8/20/20128/21/20128/22/2012 7:21:22 AMPPART
david Phone #: ###-#### project ok but needs fire final
BLD11-01943 BLD-Final8/20/20128/21/20128/22/2012 7:20:26 AMPNR
mATT bROWN Phone #: ###-####
BLD12-01916 BLD-Framing/Rough-in8/21/20128/21/20128/22/2012 7:19:55 AMPNR
gil Phone #: ###-#### needs city set of plans on site
BLD12-00999 BLD-Foundation8/21/20128/21/20128/22/2012 7:19:22 AMPPART
Shaft walls Phone #: ###-#### >> Inspection requested via web by ryan steinwand elevator pit walls ok to place concrete
BLD12-02067 BLD-Framing/Rough-in8/20/20128/21/20128/22/2012 7:18:33 AMAFAIL
Thanks Matt, Phone #: ###-#### >> Inspection requested via web by Richard Schultz needs elec rough in
BLD12-01658 BLD-Final8/21/20128/21/20128/21/2012 1:45:26 PMPPASS
chris Phone #: ###-####
BLD12-01658 BLD-Final8/21/20128/21/20128/21/2012 1:45:13 PMPPASS
Chris Phone #: ###-####
BLD12-00988 BLD-Framing/Rough-in8/21/20128/21/20128/21/2012 12:14:03 PMPDONE
Rollo Phone #: ###-####
BLD12-01658 BLD-Final8/20/20128/21/20128/21/2012 11:01:43 AMANR
chris Phone #: ###-####
BLD12-02007 BLD-Conference8/20/20128/21/20128/21/2012 10:56:27 AMAPASS
Joe Phone #: ###-####
BLD12-00763 BLD-Energy code compliance8/20/20128/21/20128/21/2012 9:14:20 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Clint Wall
BLD12-01212 BLD-Final8/20/20128/21/20128/21/2012 8:54:17 AMAPASS
First thing AM - Janet Phone #: ###-####
BLD12-01212 DOC - Permit Finaled8/21/20128/21/20128/21/2012 8:54:07 AMPPASS