BLD14-01104
| BLD-Other | 8/20/2014 | 8/21/2014 | 8/21/2014 3:45:45 PM | P | PASS |
|
|
Rebar - Ken Phone #: ###-####. INterior thickend footings.
|
BLD14-01105
| BLD-Other | 8/20/2014 | 8/21/2014 | 8/21/2014 3:45:28 PM | P | PASS |
|
|
Rebar - Ken Phone #: ###-####. INterior thickend footings.
|
BLD14-01106
| BLD-Other | 8/20/2014 | 8/21/2014 | 8/21/2014 3:45:08 PM | P | PASS |
|
|
Rebar - Ken Phone #: ###-####. INterior thickend footings.
|
BLD14-01357
| BLD-Final | 8/19/2014 | 8/21/2014 | 8/21/2014 3:04:19 PM | P | NR |
|
|
Curt Phone #: ###-####. Needs fire/life/safety final.
|
BLD13-03527
| BLD-Energy code compliance | 8/20/2014 | 8/21/2014 | 8/21/2014 3:03:49 PM | P | PASS |
|
|
Pleas call brian prior Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD13-03526
| BLD-Framing/Rough-in | 8/20/2014 | 8/21/2014 | 8/21/2014 3:03:35 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD13-03544
| BLD-Framing/Rough-in | 8/20/2014 | 8/21/2014 | 8/21/2014 3:03:13 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD13-03543
| BLD-Framing/Rough-in | 8/20/2014 | 8/21/2014 | 8/21/2014 3:02:10 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by Brian Stark
|
BLD14-02327
| BLD-Final | 8/21/2014 | 8/21/2014 | 8/21/2014 1:42:33 PM | P | NR |
|
|
An email confirmation had been sent to Mike Jordan that the electrical final had been passed. Phone #: ###-#### Inspection requested via web by James Shervik. Needs electrical final.
|
BLD14-02377
| BLD-Final | 8/20/2014 | 8/21/2014 | 8/21/2014 1:05:19 PM | P | NR |
|
|
Dan Phone #: ###-####
|
BLD14-00209
| BLD-Wall Bracing | 8/20/2014 | 8/21/2014 | 8/21/2014 9:47:27 AM | A | PASS |
|
|
richard Phone #: ###-####. 2nd. floor straps ok.
|
GCB14-00039
| GCB-Framing | 8/20/2014 | 8/21/2014 | 8/21/2014 8:57:48 AM | A | PASS |
|
|
dry wall/sheer wall inspection-Mike ###-#### . 2hr. fire wall ok.
|