ELE18-03172
| Electrical Rough-In | 8/21/2018 | 8/21/2018 | 8/21/2018 2:12:57 PM | P | PASS |
|
|
Home owner will be home after 1:00 Phone #: ###-#### Inspection requested via web by Terry Scott...new bathroom...open walls wired...ok to cover
|
ELE18-03180
| Final | 8/21/2018 | 8/21/2018 | 8/21/2018 1:18:24 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wilson...new 30A cicuit to existing disconnect..wire and Ocpd correct..ok to final.
|
ELE18-03130
| Electrical Rough-In | 8/21/2018 | 8/21/2018 | 8/21/2018 12:24:21 PM | P | PASS |
|
|
Trench inspection Phone #: ###-#### Inspection requested via web by steve ragan...underground for gate 120V and control wires...ok to cover
|
ELE18-01684
| Electrical Rough-In | 8/20/2018 | 8/21/2018 | 8/21/2018 10:42:16 AM | A | PASS |
|
|
Eron Phone #: ###-####...power for island outlet...ok to lay floor and cover
|
ELE18-00964
| ELE-Request for Extension | 8/20/2018 | 8/21/2018 | 8/21/2018 10:02:44 AM | A | PASS |
|
|
Mitch Phone #: ###-####...romodel still under construction
|
ELE17-00989
| Final | 8/21/2018 | 8/21/2018 | 8/21/2018 9:46:36 AM | A | PASS |
|
|
ok to final service
|
ELE18-03154
| Electrical Rough-In | 8/20/2018 | 8/21/2018 | 8/21/2018 9:29:05 AM | A | PASS |
|
|
Rough In and Under ground Inspection any questions please call Louis at ###-#### Phone #: ###-#### Inspection requested via web by Louis Keller....underground ok to cover and rough of shop ok to cover
|
ELE18-02499
| Permanent Service | 8/21/2018 | 8/21/2018 | 8/21/2018 9:03:20 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by JENNY EMEL...not ready...available fault current labelling and ARC flash needed
|