Inspections for the day of: Wednesday, August 22, 2007.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAimee Hughes
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC06-01911 BMP Violation8/20/20078/22/20078/22/2007 3:57:03 PMACANC
ESC06-01517 BMP Violation8/20/20078/22/20078/22/2007 3:56:51 PMACANC
ESC07-00702 Conference8/22/20078/22/20078/22/2007 2:41:59 PMPPART
Met with RP on site and ditch rider to discuss water schedule. Sediment barriers are being installed to prevent further issues on site. Will reinpsect site next week to ensure that bmp's are being maintained as necessary.
ESC07-00702 BMP Violation8/22/20078/22/20078/22/2007 2:41:33 PMPPART
Met with RP on site and ditch rider to discuss water schedule. Sediment barriers are being installed to prevent further issues on site. Will reinpsect site next week to ensure that bmp's are being maintained as necessary.
ESC06-01518 Site Final8/22/20078/22/20078/22/2007 10:38:42 AMPPASS
Final stabilization has been completed.
ESC06-01310 BMP Violation8/20/20078/22/20078/22/2007 10:24:00 AMAPART
Met with RP to reinspect site. Issues on c/n have been addressed. Silt fence along Crescent Line will be removed when road work is completed this week. All other issues have been addressed.
ESC07-00702 BMP Violation8/20/20078/22/20078/22/2007 9:59:58 AMAFAIL
Sediment barriers are still not in place. Water in ditch is preventing sediment barriers from being installed. Contacted ditch rider about water schedule. Flood gate will be shut by noon today and water level will decrease enough for barriers to be installed.
ESC07-00117 Complaint Inspection8/22/20078/22/20078/22/2007 9:31:22 AMPFAIL
Notified RP of citizen complaint regarding dust. Forwarded complaint to DEQ as well. All other bmp's are being maintained.