MEC95-00117
| INSP - Framing/ Rough-in | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | A | PASS |
|
|
08/23/96 337 - FNL -OK FINAL
|
MEC96-00134
| INSP - Framing/ Rough-in | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | A | PASS |
|
|
08/23/96 337 - ta 1 (ri) building call greg at 97940 this permit shows i don't understand this job was finaled 1/16/96
|
MEC96-02341
| INSP - Final | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | A | NR |
|
|
08/23/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED NOT READY
|
MEC96-02341
| INSP - Final | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | A | NR |
|
|
08/23/96 337 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED NOT READY
|
MEC96-02273
| INSP - Rough-in & Gas Pressure | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | A | NH |
|
|
08/23/96 337 - REINSPECTION UGA -UNABLE TO GAIN ACCESS-LEFT NOTC
|
MEC96-02338
| INSP - Framing/ Rough-in | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | P | PART |
|
|
08/23/96 337 - 8-23-96 PM. THE LATER THE BETTER. RE-INSPECTION PARTIAL R/I OK OK FOR COVER EXCEPT MECH ROOM
|
MEC96-02376
| INSP - Retro Fit (check note) | 8/23/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | P | PASS |
|
|
08/23/96 337 - PT FOR FURN AND WH/ REINSPECTION FNL -OK FINAL
|
MEC96-02394
| INSP - Gas pressure test | 8/22/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | P | PART |
|
|
08/23/96 337 - GAS TEST OK EQUIP NOT READY
|
MEC96-01863
| INSP - Framing/ Rough-in | 8/23/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | P | PASS |
|
|
08/23/96 337 - FNL -OK FINAL
|
MEC96-01863
| INSP - Gas pressure test | 8/23/1996 | 8/23/1996 | 8/23/1996 12:00:00 AM | P | PASS |
|
|
08/23/96 337 - FNL -OK FINAL
|