ELE99-02690
| Electrical Rough-In | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | A | PART |
|
|
kent ###-#### conference only
|
ELE00-03252
| Temporary Service | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | A | PASS |
|
|
###-####
|
ELE00-02313
| Final | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 13:01:32. Contact: ###-####.
|
ELE00-02114
| Final | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 15:27:12. Contact: ###-####.
|
ELE00-03227
| Temporary Service | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | A | PASS |
|
|
###-#### reinspection
|
ELE00-03250
| Temporary Service | 8/23/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 08:31:01. Contact: ###-####.
|
ELE00-03272
| Electrical Rough-In | 8/23/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | P | PART |
|
|
ed--###-#### post lighting-underground --for complex -"7" LIGHTS
|
ELE00-03222
| Electrical Rough-In | 8/23/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 10:03:41. Contact: ###-####.
|
ELE00-03159
| Electrical Rough-In | 8/23/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | P | FAIL |
|
|
Lesley ###-#### posted correct open job 8/24/2000 7:48:49 AM
|
ELE99-04105
| Electrical Rough-In | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 14:26:21. Contact: .
|
ELE00-02204
| Electrical Rough-In | 8/22/2000 | 8/23/2000 | 8/23/2000 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 14:50:25. Contact: .
|