BLD03-02347
| Extend Permit 180 days | 8/20/2007 | 8/20/2007 | | P | |
|
|
|
FIR07-00166
| INSP-Alarm Testing | 8/22/2007 | 8/23/2007 | 8/23/2007 5:00:24 PM | A | FAIL |
|
|
Overspaced SD at the cafeteria, strobe coverage is lacking at one area in the kitchen, audibility is too low for the kitchen service/prep area, remainder of the 4th floor west half as tested is acceptable.
|
BLD07-01043
| FIRE-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 3:35:26 PM | P | FAIL |
|
|
Pending project related fire sprinkler permit final.
|
FIR07-00474
| INSP-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 3:34:00 PM | P | FAIL |
|
|
Work is not complete.
|
FIR07-00620
| INSP-Sprinkler Rough-in | 8/22/2007 | 8/23/2007 | 8/23/2007 3:14:35 PM | A | FAIL |
|
|
See approved plans for areas inspected and noted defficiences including overspaced heads at an office and equip. room, missing hangers at two arm-overs, and missing heads at three closets.
|
BLD07-01658
| FIRE-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 2:36:05 PM | P | PASS |
|
|
Fire life safety inspection passed.
|
FIR07-00233
| INSP-Sprinkler Rough-in | 8/22/2007 | 8/23/2007 | 8/23/2007 2:12:34 PM | A | PART |
|
|
UG fire supply line from the stub in at the foundation to the PIV only is okay for cover. Also inspected UG fire supply lines for the other three buildings not separately requested for inspection under respective FIR #'s as will be required for hydrostatic and flushing inspections.
|
FIR07-00460
| INSP-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 1:53:58 PM | P | CANC |
|
|
No time available to complete this inspection today, to be rescheduled.
|
BLD07-00292
| FIRE-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 1:52:48 PM | P | NR |
|
|
Intended for an on site conference, to be scheduled as discussed.
|
BLD07-00623
| FIRE-Alarm Testing | 8/22/2007 | 8/23/2007 | 8/23/2007 1:42:09 PM | A | PASS |
|
|
Request intended for fire life safety final. Fire life safety is acceptable, need to install smoke seal at the door prior to structural final-to be completed when door frame paint is finished per contractor.
|
BLD07-01679
| FIRE-Final Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 12:48:57 PM | P | PASS |
|
|
Life safety inspection passed.
|
BLD07-00808
| FIRE-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 11:57:28 AM | A | PASS |
|
|
Fire life safety is acceptable pending the addition of two PFE's on the mezzanine level, also need to blank keyed locks above the panic hardware, these two items shall be completed prior to structural final-verified at that time.
|
FIR07-00141
| INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 11:17:11 AM | A | PART |
|
|
Overhead rough in is good for cover at the hard lid ceiling areas, changes to floor plan are noted.
|
FIR07-00142
| INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 11:15:54 AM | A | PART |
|
|
OH install is approved for cover at the hard lid ceilings, floor plan changes noted.
|
FIR07-00149
| INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 11:14:52 AM | A | PART |
|
|
OH install is approved for cover, noted some changes to floor plan are acceptable.
|
FIR07-00145
| INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 11:13:05 AM | A | FAIL |
|
|
Missing sprinkler protection at one closet which exceeds dimentions allowed for coverage omission, remainder of ceilings are okay for cover.
|
FIR07-00150
| INSP-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 11:09:07 AM | A | FAIL |
|
|
One head is blocked by ductwork at a mech. closet, pendent at the kitchen area must meet obstruction tables for proximity to an adjacent soffit, remainder of ceilings are okay for cover.
|
FIR06-00007
| INSP-Final Inspection | 8/21/2007 | 8/23/2007 | 8/23/2007 10:07:21 AM | A | CANC |
|
|
No time available to complete this inspection today, rescheduled for 8/24 AM as agreed.
|
BLD06-03408
| FIRE-Final Inspection | 8/22/2007 | 8/23/2007 | 8/23/2007 10:05:38 AM | A | PASS |
|
|
Corrections are complete, fire life safety inspection passed.
|
FIR07-00029
| FIR-Aging Inspection | 8/23/2007 | 8/23/2007 | 8/23/2007 9:47:24 AM | | DEFR |
|
|
Work in progress.
|