Inspections for the day of: Tuesday, August 23, 2016.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD16-02969 FIRE-Final Inspection8/23/20168/23/20168/23/2016 2:15:05 PMPCANC
would like call ahead; Jim Phone #: ###-####
BLD16-02969 FIRE-Final Inspection8/17/20168/23/20168/23/2016 2:07:55 PMAPASS
Life safety passed
BLD16-00743 FIRE-Final Inspection8/23/20168/23/20168/23/2016 1:10:16 PMPFAIL
Provide fire sprinkler permit for required modifications
NAF16-00049 INSP-Final8/22/20168/23/20168/23/2016 1:09:46 PMPPASS
Life safety passed. The contractor stated that passage hardware was to be installed for exiting the island restroom corridor.
BLD16-02787 FIRE-Final Inspection8/19/20168/23/20168/23/2016 10:12:16 AMAFAIL

To receive a final life safety for the above referenced project an annual inspection needs to be performed on the existing fire sprinkler system. All so a permit needs to be submitted to the city of Boise for the work already performed on the existing fire alarm system. Once this permit has been submitted and issued I need to perform an inspection on the work for code and listing compliance.
BLD16-02446 FIRE-Final Inspection8/22/20168/23/20168/23/2016 9:17:45 AMAPASS
Life safety passed. Per approved upgrade agreement letter in place with Boise City and Boise City Fire Department. Approved by Ron Johnson and Jason Blais.
BLD15-01921 FIRE-Final Inspection8/23/20168/23/20168/23/2016 8:33:28 AMAPASS
life safety passed
FIR15-00892 INSP-Final Inspection8/22/20168/23/20168/23/2016 8:28:03 AMAPASS
permit finaled