Inspections for the day of: Friday, August 23, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-01856 Final8/23/20198/23/20198/23/2019 2:56:09 PMPPASS
Phone #: ###-#### Inspection requested via web by Emmet Bushman
Final ok
ELE19-02763 Electrical Rough-In8/22/20198/23/20198/23/2019 2:12:12 PMPPASS
Ceiling inspection Phone #: ###-#### Inspection requested via web by Deb Ipsen
Ceiling ok to cover
ELE19-02766 Electrical Rough-In8/22/20198/23/20198/23/2019 2:11:03 PMPPASS
Ceiling inspection Phone #: ###-#### Inspection requested via web by Deb Ipsen
Ceiling ok to cover
ELE19-03163 Temporary Service8/23/20198/23/20198/23/2019 2:10:33 PMPPASS
Chris- late afternoon please Phone #: ###-####
t/s o/h n ok
ELE18-04054 Electrical Rough-In8/22/20198/23/20198/23/2019 1:07:48 PMAPASS
Contact: Mike Mulvahill Phone #: ###-#### Inspection requested via web by Deb Gooden
Fire Riser room walls ok to cover
ELE19-02614 Electrical Rough-In8/22/20198/23/20198/23/2019 10:11:49 AMACANC
Solar Panel install. Our guys will be there to install that morning. --Amy Phone #: ###-#### Inspection requested via web by Amy Simms
Nobody on site
ELE19-02979 Final8/19/20198/23/20198/23/2019 9:49:42 AMAPASS
Joseph Phone #: ###-####
Solar Array final ok
ELE19-02979 Electrical Rough-In8/22/20198/23/20198/23/2019 9:49:17 AMAPASS
Joseph Phone #: ###-####
As approved plans on site all components are U/L listed, Warned contractor about process of inspection for solar array rough-in requirements proir to finals, licenses checked as well
ELE19-03166 Final8/22/20198/23/20198/23/2019 9:28:43 AMAPASS
Phone #: ###-#### Inspection requested via web by Ryan Wilson
A/C units final ok
ELE19-03139 Electrical Rough-In8/22/20198/23/20198/23/2019 8:57:33 AMAPASS
Contact Preston Seay with any questions ###-#### Phone #: ###-#### Inspection requested via web by Rob Maes
Verified U/L listing and scope of work for Solar Array install