PLM4045960
| INSP - Final | 8/23/1995 | 8/24/1995 | 8/24/1995 12:00:00 AM | A | PASS |
|
|
08/24/95 330 - temp occ ok need prv 20-wc,20-lav,10-sh,10-tub,10si,10-wb,10-wh,1-dcva
|
PLM4047358
| INSP - Final | 8/24/1995 | 8/24/1995 | 8/24/1995 12:00:00 AM | P | FAIL |
|
|
08/24/95 330 - correction: provide access to wh, test dcva
|
PLM95-00551
| INSP - Plumbing Rough-in | 8/24/1995 | 8/24/1995 | 8/24/1995 12:00:00 AM | P | PASS |
|
|
08/24/95 330 - r/i ok 2-wc,2-lav,1-tub,1-sh,1-si,1-wb,1-wh,,future fixtures 1-wc,1-lav,1-sh.
|
PLM95-00720
| INSP - Sewer and Water lines | 8/24/1995 | 8/24/1995 | 8/24/1995 12:00:00 AM | P | PASS |
|
|
08/24/95 330 - s/w ok
|
PLM95-00722
| INSP - Sprinkler & Backflow | 8/24/1995 | 8/24/1995 | 8/24/1995 12:00:00 AM | P | PASS |
|
|
08/24/95 330 -
|
PLM95-00723
| INSP - Ground Work/Sewer/Water | 8/24/1995 | 8/24/1995 | 8/24/1995 12:00:00 AM | P | PASS |
|
|
08/24/95 330 - partial g/w ok deep main only
|