Inspections for the day of: Friday, August 24, 2007.
Number of inspections: 15
Percentage of inspections complete: 93 %
Percentage of inspections not complete: 7 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD03-02347 Extend Permit 180 days8/20/20078/20/2007 P 
FIR07-00690 INSP-Final Inspection8/24/20078/24/20078/27/2007 5:19:56 PMPFAIL
HVAC is not wired to the duct detector to enable shutdown of the unit.
FIR07-00148 FIR-Aging Inspection8/24/20078/24/20078/27/2007 10:59:14 AM DEFR
Work in progress.
BLD06-02000 FIRE-Final Inspection8/24/20078/24/20078/27/2007 9:33:34 AMPDEFR
###-#### - derick
BLD07-00292 FIRE-Conference8/23/20078/24/20078/24/2007 4:30:03 PMPNH
Contractor not available on site or telephone at the time of field visit.
BLD07-01043 FIRE-Final Inspection8/23/20078/24/20078/24/2007 4:18:48 PMANR
Project related fire sprinkler permit failed inspection.
FIR07-00474 INSP-Final Inspection8/24/20078/24/20078/24/2007 4:18:02 PMPFAIL
Overspaced heads at four locations.
FIR07-00448 INSP-Sprinkler Rough-in8/23/20078/24/20078/24/2007 2:55:19 PMPFAIL
Insulation at the roof deck is still obstructing upright head coverage, also missing cold cavity protection at the concealed spaces above the riser and lobby.
FIR06-00007 INSP-Final Inspection8/23/20078/24/20078/24/2007 2:47:25 PMAPART
1st floor fire alarm testing completed today, items remaining for the 1st floor include lacking HD at the elevator machine room and missing main FACP door.
FIR06-00759 INSP-Final Inspection8/22/20078/24/20078/24/2007 12:55:14 PMPPART
Pressure relief valve, test header and associated piping install completed satisfactory, final pending functional testing of the PRV.
BLD07-01120 FIRE-Final Inspection8/23/20078/24/20078/24/2007 11:49:32 AMAPASS
Noted corrections have been completed, TI modification fire life safety inspection passed.
FIR07-00166 INSP-Alarm Testing8/23/20078/24/20078/24/2007 11:47:24 AMAPART
Re-inspection for the fire alarm work associated with the 4th floor remodel BLD07-01120 passed, remainder of alarm permit scope of work not yet completed.
FIR07-00460 INSP-Final Inspection8/23/20078/24/20078/24/2007 11:44:48 AMAPASS
Required corrections have been verified for compliance, final alarm testing passed, permit finaled.
FIR07-00645 INSP-Final Inspection8/24/20078/24/20078/24/2007 11:43:16 AMAPASS
Fire sprinkler permit work passed final inspection.
BLD07-01374 FIRE-Final Inspection8/23/20078/24/20078/24/2007 11:42:03 AMAFAIL
Need to provide visual indicator at the main entry/exit door, EM lighting at the warehouse area failed to function.