Inspections for the day of: Wednesday, August 24, 2016.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00435 INSP-Sprinkler Rough-in8/24/20168/24/20168/24/2016 1:30:34 PMPPART
Rough-in passed except for one head that is missing in a second floor west end restroom. No tenting has been installed or inspected so no piping can be covered.
NAF16-00034 INSP-Conference8/24/20168/24/20168/24/2016 1:28:00 PMPDONE
Went over underground supply bury requirements.
BLD15-04264 FIRE-Conference8/24/20168/24/20168/24/2016 1:16:19 PMPDONE
Jeff and I went over life safety requirements. See the fire review notes for items marked ok and items circled that need addressed for a final inspection.
FIR16-00443 INSP-Sprinkler Rough-in8/23/20168/24/20168/24/2016 10:54:23 AMACANC
No approved drawings and per conversation it appears plans will need to be re-submitted.
FIR16-00439 INSP-Sprinkler Rough-in8/23/20168/24/20168/24/2016 10:53:44 AMAFAIL
Plans need to be re-submitted showing all of the pipe routing changes and additional fittings. No tenting has been completed. No rough-in inspection performed due to changes.
FIR16-00107 INSP-Final Inspection8/23/20168/24/20168/24/2016 9:15:08 AMAFAIL
Provide seismic bracing at the 19' level of the new riser as per the approved plans.
FIR16-00117 INSP-Final Inspection8/23/20168/24/20168/24/2016 9:14:31 AMAFAIL
Provide siesmic bracing at the old riser location and provide clearance at wall penatration at the same location.
FIR15-00828 INSP-Final Inspection8/23/20168/24/20168/24/2016 9:13:19 AMAPASS
Permit finaled