Inspections for the day of: Wednesday, August 24, 2016.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00545 INSP-Final Inspection8/24/20168/24/20168/24/2016 1:47:20 PMPPASS
Final fire sprinkler inspection per this area of work passed/complete.
FIR16-00322 INSP-Sprinkler Rough-in/Hydro8/23/20168/24/20168/24/2016 1:24:37 PMPFAIL
Overhead fire sprinkler piping not ready for hydrostatic test, multiple leaks throughout the sprinkler system. Hydrostatic test will need to be rescheduled after repairs are made.
FIR16-00362 INSP-Final Inspection8/24/20168/24/20168/24/2016 12:45:56 PMPPASS
Final fire alarm inspection passed/complete.
BLD15-01112 FIRE-Final Inspection8/23/20168/24/20168/24/2016 9:19:37 AMAPART
Partial final life fire safety inspection passed/complete, fire sprinkler inspection is partially complete, reference to activites under FIR16-00028 for fire sprinkler comments. Dry standpipe inspection for this building is complete. Partial final inspection complete for fire alarm system, reference activities under FIR16-00400 for fire alarm comments. A partial final for life fire safety inspection is complete, monitored heat trace associated with fire alarm and fire sprinkler system needs to be installed and inspected/passed for life fire safety to be finaled. Fire extinguishers are in place with current inspection tags. A 60 day TCO is authorized per conversation with Scott Arellano.
FIR16-00400 INSP-Final Inspection8/24/20168/24/20168/24/2016 9:08:55 AMAPART
Partial final inspection for fire alarm system complete. All tamper switches and flow switches associated fire sprinkler have been inspected/passed. Sub-panel associated with building O reported to clubhouse fire panel with proper address identification for devices. Monitored heat tape will be installed at a later date to prevent fire sprinkler piping that crosses the breezeway on each level from freezing. Fire alarm permit can be finaled after freezing prevention has been installed/inspected and passed. A 60 dy TCO is authorized per conversation with Scott Arellano.
FIR16-00218 INSP-Final Inspection8/22/20168/24/20168/24/2016 9:03:00 AMAPASS
Final inspection for dry standpipe complete, knox caps are on order and will be installed when received. Hose valve caps will be installed towards the end of the apartment complex completion to prevent theft of the brass.
FIR16-00028 INSP-Final Inspection8/22/20168/24/20168/24/2016 9:00:18 AMAPART
Partial final fire spinkler inspection passed/complete. Each level of the building has fire sprinkler piping that crosses the breezeway, an approved method of keeping the pipe from freezing needs to be installed and inspected before final inspection can be completed. Fire sprinkler inspection is complete for remainder of building. TCO authorized for 60 days per conversation with Scott Arellano.
BLD16-00666 FIRE-Final Inspection8/24/20168/24/20168/24/2016 8:01:30 AMAPASS
Fire sprinkler inspection is complete, fire alarm inspection is complete, commercial hood fire suppression system inspection is complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIR16-00550 INSP-Final Inspection8/23/20168/24/20168/24/2016 7:59:46 AMAPASS
Previously noted items have been addressed, final fire alarm inspection passed/complete
BLD16-03073 FIRE-Final Inspection8/23/20168/24/20168/23/2016 3:24:56 PMACANC
Duplicate inspection request, life fire safety inspection is complete.