Inspections for the day of: Friday, August 25, 1995.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAlan Hauser
TitleMEC-COM/RES INSPECTOR
Phone #794-9453
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC95-00317 INSP - Water heater8/25/19958/25/19958/25/1995 12:00:00 AM PASS
/ / 350 - w/h ok
MEC95-00317 INSP - Framing/ Rough-in8/25/19958/25/19958/25/1995 12:00:00 AM PASS
/ / 350 - FURN-FURNACE OK
MEC95-00661 INSP - Framing/ Rough-in8/25/19958/25/19958/25/1995 12:00:00 AM PASS
/ / 350 - FURN-FURNACE OK
MEC95-00677 INSP - Gas pressure test8/25/19958/25/19958/25/1995 12:00:00 AM PASS
/ / 350 - GP -OK GAS PIPING #27930
MEC95-00677 INSP - Framing/ Rough-in8/25/19958/25/19958/25/1995 12:00:00 AM PASS
/ / 350 - RGHN-OK ROUGH IN
MEC95-00317 INSP - Gas pressure test8/24/19958/25/19958/25/1995 12:00:00 AMAFAIL
08/24/95 350 - gas was witnessed by gas company
MEC95-00661 INSP - Gas pressure test8/24/19958/25/19958/25/1995 12:00:00 AMAPASS
08/24/95 350 - GP -OK GAS PIPING #27939
MEC95-00261 INSP - Gas pressure test8/25/19958/25/19958/25/1995 12:00:00 AMPPASS
08/25/95 350 - GP -OK GAS PIPING #27928
MEC95-00671 INSP - Rough-in & Gas Pressure8/25/19958/25/19958/25/1995 12:00:00 AMPPASS
08/25/95 350 - RGHN-OK ROUGH IN GP -OK GAS PIPING #27932
MEC95-00672 INSP - Rough-in & Gas Pressure8/25/19958/25/19958/25/1995 12:00:00 AMPPASS
08/25/95 350 - r/i ok all four units GP -OK GAS PIPING #27938, 27934, 27935, 27936 4 of 4
MEC95-00673 INSP - Rough-in & Gas Pressure8/25/19958/25/19958/25/1995 12:00:00 AMPPASS
08/25/95 350 - RGHN-OK ROUGH IN GP -OK GAS PIPING #27931
MEC95-00391 INSP - Final8/25/19958/25/19958/25/1995 12:00:00 AMPNR
08/25/95 350 - not ready check monday morning
MEC95-00391 INSP - Final8/25/19958/25/19958/25/1995 12:00:00 AMPNR
08/25/95 350 - not ready check monday morning
MEC95-00597 INSP - Framing/ Rough-in8/25/19958/25/19958/25/1995 12:00:00 AMPPASS
08/25/95 350 - RGHN-OK ROUGH IN union in attic was sealed with lock tight.
MEC95-00610 INSP - Final8/25/19958/25/19958/25/1995 12:00:00 AMPFAIL
08/25/95 350 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gas piping failed it is under have 195,000 btus at 128' 3/4" pipe need 11/4"
MEC95-00610 INSP - Final8/25/19958/25/19958/25/1995 12:00:00 AMPFAIL
08/25/95 350 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED gas piping failed it is under have 195,000 btus at 128' 3/4" pipe need 11/4"
MEC95-00660 INSP - Final8/25/19958/25/19958/25/1995 12:00:00 AMPFAIL
08/25/95 350 - no final all the work was done with out a permit. double
MEC95-00660 INSP - Final8/25/19958/25/19958/25/1995 12:00:00 AMPFAIL
08/25/95 350 - no final all the work was done with out a permit. double