PLM00-02879
| Plumbing Rough-in | 8/23/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 11:53:37. Contact: ###-####.
|
PLM00-03012
| Plumbing Rough-in | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | FAIL |
|
|
###-#### owner said she wasn't ready when I got there 8/25/2000 1:25:50 PM
|
PLM00-03014
| Water and/or Sewer | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PASS |
|
|
Russ ###-####
|
PLM00-02493
| Final | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | FAIL |
|
|
###-#### unapproved airgaps at soap dispensors, and avb at mop sink is under pressure for more than 12 hours 8/25/2000 1:24:37 PM
|
PLM00-03018
| Plumbing Rough-in | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PASS |
|
|
Lorinda ###-####
|
PLM00-02169
| Groundwork | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/24/2000 at 14:30:42. Contact: ###-####.
|
PLM00-01619
| Final | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PASS |
|
|
lock EHC front door lock rick ###-####
|
PLM00-01159
| Final | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 08/24/2000 at 16:33:43. Contact: ###-####. air gap t&p drain complete fixture installition 8/25/2000 1:26:25 PM
|
PLM00-03017
| Plumbing Rough-in | 8/24/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PART |
|
|
john hardy-- ###-#### r/i partial gw ok still needs branch line to main 8/25/2000 1:25:12 PM
|
PLM00-02400
| Water and/or Sewer | 8/25/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | A | PART |
|
|
Added by Inspector: 330 On 8/25/2000 2 sections that failed passed on section W
|
PLM00-03026
| Plumbing Rough-in | 8/25/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM00-01159
| Final | 8/25/2000 | 8/25/2000 | 8/25/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/25/2000 at 10:56:05. Contact: ###-####.
|