BLD03-00452
| FIRE-Final Inspection | 8/20/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | A | PASS |
|
|
nick; Phone #: ###-#### Fire life safety finaled. Contractor still needed to hang the two upstairs apartment doors. Structural inspector to please verify. 8/25/2003 2:31:26 PM
|
BLD03-01233
| FIRE-Final Inspection | 8/21/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | A | FAIL |
|
|
steve; Phone #: ###-#### Provide lever hardware on the door in reception office 8/25/2003 12:16:19 PM
|
MIS03-00158
| FIR-Final | 8/21/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | A | PASS |
|
|
fire life safety finaled 8/25/2003 10:43:16 AM
|
BLD02-00730
| FIRE-Sprinkler Rough-in | 8/22/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | A | PART |
|
|
See the approved plans for the rooms that the sprinkler pipig is OK to cover. Also see plans for location of sprinkler pendant that needs replaced, closet with missing pendant and the Soiled Linen room should be ordinary hazard spacing not light hazard 8/25/2003 10:59:17 AM
|
FIR03-00474
| INSP-Sprinkler Rough-in | 8/22/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | A | PART |
|
|
Underground sprinkler piping is OK to cover 8/25/2003 10:47:09 AM
|
FIR03-00376
| INSP-Sprinkler Rough-in/Hydro | 8/25/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | P | PART |
|
|
sam; Phone #: ###-#### The remaining underground supply piping is ok to cover on the north building 8/25/2003 3:20:09 PM
|
FIR03-00350
| INSP-Final Inspection | 8/25/2003 | 8/25/2003 | 8/25/2003 12:00:00 AM | P | FAIL |
|
|
provide annual ispection for the fire sprinkler system and hydraulic placard for the new system to be placed at the riser 8/25/2003 4:39:26 PM
|