FIR05-00463
| INSP-Final Inspection | 8/25/2005 | 8/25/2005 | 8/25/2005 5:15:43 PM | P | CANC |
|
|
No time to complete inspection, rescheduled for tomorrow p.m.
|
FIR05-00493
| INSP-Supply line flush | 8/24/2005 | 8/25/2005 | 8/25/2005 5:13:46 PM | P | PART |
|
|
UG flush is satisfactory.
|
BLD05-01718
| FIRE-Final Inspection | 8/25/2005 | 8/25/2005 | 8/25/2005 4:27:11 PM | P | FAIL |
|
|
No power to HVAC units to enable testing of duct smoke detection devices, the remaining life safety issues are satisfactory.
|
BLD05-01484
| FIRE-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 3:45:03 PM | P | FAIL |
|
|
Need to repair emergency discharge light at back exit, need to mount the two fire extinguishers provided for the sales floor, need to install remaining ceiling tile and sprinkler escutcheons, provide fire alarm permit and duct smoke detectors.
|
FIR05-00458
| INSP-Sprinkler Rough-in | 8/24/2005 | 8/25/2005 | 8/25/2005 2:58:32 PM | P | PART |
|
|
Underground fire supply line riser and stub out are good for cover, the top of pipe to grade at top of stem wall is 4'-5", will verify at next inspection min. depth of bury has been met.
|
FIR05-00049
| INSP-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 2:47:40 PM | A | PASS |
|
|
Fire sprinkler permit finaled.
|
FIR05-00498
| INSP-Sprinkler Rough-in/Hydro | 8/24/2005 | 8/25/2005 | 8/25/2005 1:15:47 PM | A | FAIL |
|
|
A concealed pocket enclosed by combustible construction lacks sprinkler coverage above office 101, and restrooms 102 and 104.
|
BLD05-01993
| FIRE-Conference | 8/24/2005 | 8/25/2005 | 8/25/2005 12:30:36 PM | A | DEFR |
|
|
dave; Phone #: ###-#### On site discussion with Dave regarding exit signage, the fire sprinkler permit, fire extinguisher placement, door hardware, building address, and emergency lighting.
|
FIR05-00044
| INSP-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 11:45:14 AM | P | CANC |
|
|
Inspection has been rescheduled for friday the 26th per Jason at ###-####.
|
FIR05-00186
| INSP-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 11:40:53 AM | A | CANC |
|
|
Spoke with the contractor to reschedule this inspection for friday the 26th due to time constraints today.
|
FIR05-00273
| INSP-Sprinkler Rough-in | 8/24/2005 | 8/25/2005 | 8/25/2005 11:38:40 AM | A | FAIL |
|
|
First floor piping does not match approved drawings due to several field changes that have been made, resubmit plans reflecting the actual installation for approval prior to field inspection, the second floor rough-in is good for cover, the third floor master bedrooms each have low soffits affecting proper coverage and response time.
|
FIR05-00529
| INSP-Sprinkler Rough-in/Hydro | 8/24/2005 | 8/25/2005 | 8/25/2005 9:59:31 AM | A | PART |
|
|
Overhead rough-in is good for cover, will final permit when ceiling tile and escutcheons are installed.
|
MIS05-00125
| FIR-Final | 8/23/2005 | 8/25/2005 | 8/25/2005 8:36:37 AM | A | CANC |
|
|
Inspection canceled by contractor at ###-####, not ready, will reschedule for monday the 29th.
|
BLD05-00874
| FIRE-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 8:33:04 AM | A | FAIL |
|
|
Need to post building address, provide fire extinguisher with current inspection tag installed as discussed, provide emergency lighting as indicated on plan review notes.
|