Inspections for the day of: Tuesday, August 25, 2009.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00290 INSP-Final Inspection8/24/20098/25/20098/28/2009 4:14:48 PMACANC
Inspection request precluded by work on FIR09-00296 dated 8/25.
FIR09-00033 INSP-Sprinkler Rough-in/Hydro8/25/20098/25/20098/28/2009 1:06:18 PMPDONE
Duplicate inspection request-see activity notes for details.
FIR09-00033 INSP-Sprinkler Rough-in8/21/20098/25/20098/28/2009 1:04:54 PMAFAIL
See C/N on site for inspection comments completed 8/26 by T. Frost--System 13 had an HVAC duct blocking the sprinklers at column line C.
System 11 needs sprinklers in the doorway areas.
System 14 Ceiling tile missing through out. In the scan department of system 14 there cannot be storage on the top level of the racks.
City of Boise still has not received a letter from Peerless Pump on the malfunctioning PLD.
System 21 condensate piping is blocking a sprinkler head.
All dry storage systems. The 4x4 structural tubing has not been removed and the ESFR sprinklers are blocked.
FIR09-00033 INSP-Alarm Testing8/21/20098/25/20098/25/2009 1:50:32 PMPFAIL
Alarm Testing for preaction activation. Phone #: ###-#### Internet Inspection Request from: Jeff Packham ATTN: See notes for FIR09-00296--Deficient items found during the first three hours of inspection include missing NFPA 72 Record of Inspection and Testing with a copy of supervising station signals report per plan review note #3, missing signage per review note #1, provide a lock and label at the power circut breaker to the panel, A/C power off failed to report to the main FACP-see note #5, per details on approved plans 90 deg. ells to be avoided and 6" to 10" clearance to be provided at each side of the freezer wall to avoid ice plugs-noted significant frosting at these locations, the first VESDA fault at system 28 did not report, plans incorrectly show location of system 27, south line of smoke detection at systems 16,17, and 18 are overspaced-see fire code review note #13, provide a building map at the releasing panel indicating floorplan layout and locations of all initiating devices-see plan review note #15, repairs underway at VESDA system 29.
FIR09-00296 INSP-Final Inspection8/24/20098/25/20098/25/2009 1:47:52 PMAFAIL
Deficient items found during the first three hours of inspection include missing NFPA 72 Record of Inspection and Testing with a copy of supervising station signals report per plan review note #3, missing signage per review note #1, provide a lock and label at the power circut breaker to the panel, A/C power off failed to report to the main FACP-see note #5, per details on approved plans 90 deg. ells to be avoided and 6" to 10" clearance to be provided at each side of the freezer wall to avoid ice plugs-noted significant frosting at these locations, the first VESDA fault at system 28 did not report, plans incorrectly show location of system 27, south line of smoke detection at systems 16,17, and 18 are overspaced-see fire code review note #13, provide a building map at the releasing panel indicating floorplan layout and locations of all initiating devices-see plan review note #15, repairs underway at VESDA system 29.
FIR09-00033 INSP-Alarm Testing8/21/20098/25/20098/24/2009 12:58:48 PMANR
Pending FIR09-00296