BLD09-01268
| FIRE-Final Inspection | 8/25/2009 | 8/25/2009 | 8/25/2009 4:08:57 PM | P | PASS |
|
|
Life safety passed.
|
FIR09-00453
| INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 4:08:37 PM | P | FAIL |
|
|
The duct smoke detectors could not be tested due to the contractor not being able to start the hvac units in heat mode.
|
FIR09-00164
| INSP-Sprinkler Rough-in/Hydro | 8/25/2009 | 8/25/2009 | 8/25/2009 4:04:40 PM | P | PASS |
|
|
The sprinkler piping in the interstitial space and the attic area passed inspection. Steve and I noted several chase doors that will need to be removed/permanantly closed that are obstructing attic sprinklers. Several shipping caps had been left on the uprights and steve will go through the system and re-verify that all have been removed. Viking was in the process of lenghtening several sprig ups and providing additional hangers at arm-overs in the interstitial space.
|
FIR09-00396
| INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 4:01:24 PM | P | PASS |
|
|
Permit finaled
|
BLD09-01062
| FIRE-Final Inspection | 8/25/2009 | 8/25/2009 | 8/25/2009 4:00:55 PM | P | CANC |
|
|
The life safety could not be completed due to time constraints and the project related fire alarm and fire sprinkler permits not being completed. I also noted that several doors/hardware had not been installed.
|
BLD09-01062
| FIRE-Alarm Testing | 8/25/2009 | 8/25/2009 | 8/25/2009 4:00:33 PM | P | CANC |
|
|
The life safety could not be completed due to time constraints and the project related fire alarm and fire sprinkler permits not being completed. I also noted that several doors/hardware had not been installed.
|
FIR09-00451
| INSP-Final Inspection | 8/25/2009 | 8/25/2009 | 8/25/2009 3:58:47 PM | P | FAIL |
|
|
None of the items tested passed due to the monitoring station not receiving the correct signals. All of the items tested today will need to be retested. Also several of the hvac units/duct smoke detectors could not be tested due to the gas meter being locked. Also Allied General was not complete with the releasing system that is interconnected with this new panel.
|
BLD09-01411
| FIRE-Final Inspection | 8/25/2009 | 8/25/2009 | 8/25/2009 3:51:53 PM | P | PART |
|
|
Provide annual inspection for the fire extinguishers, provide single action hardware for the double doors out of the new tenant area and provide emergency lighting in the new tenant area.
|
FIR08-00831
| INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 12:55:13 PM | A | FAIL |
|
|
Todays inspection was a rough-in inspection for the first and second floor corridors where the piping is ok to cover. The central core areas still need to be completed on both floors.
|
FIR08-00832
| INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 12:36:43 PM | A | FAIL |
|
|
Todays inspection was a rough-in inspection for the first and second floor corridors where the piping is ok to cover. The central core areas still need to be completed on both floors.
|
BLD09-01402
| FIRE-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 9:38:08 AM | A | PASS |
|
|
Life safety passed
|
BLD09-01402
| FIRE-Alarm Testing | 8/24/2009 | 8/25/2009 | 8/25/2009 9:37:22 AM | A | CANC |
|
|
Fire alarm testing not required. Life safety passed.
|
BLD09-00896
| FIRE-Final Inspection | 8/25/2009 | 8/25/2009 | 8/25/2009 9:05:17 AM | P | CANC |
|
|
Wrong inspection type called in. A building final was needed.
|
FIR09-00343
| INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 8:43:33 AM | A | FAIL |
|
|
The smoke detector closest to the entry door needs to be relocated atleast 3' from the supply register and test for functionality. All other items tested ok. The operation sequence for the releasing panel had to be changed as I waited so that only one initiating device is required to trip the pre-action system.
|
FIR09-00430
| INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 8:41:08 AM | A | PASS |
|
|
Permit finaled
|