Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD11-00610 FIRE-Conference8/17/20118/22/2011 A 
Troy-call Dixie for am meeting
BLD11-00781 FIRE-Conference8/25/20118/25/20118/25/2011 3:39:06 PMPDONE
Went over racking issues with Chris Palmer
FIR11-00426 INSP-Sprinkler Rough-in8/24/20118/25/20118/25/2011 2:01:47 PMPPASS
Rough-in passed
BLD11-01104 FIRE-Final Inspection8/24/20118/25/20118/25/2011 12:25:07 PMAFAIL
Provide a manual fire alarm system. Provide tagged and mounted fire extinguisher as discussed. Applicant needs to meet with the plan reviewer to discuss which two exits will be the required exits. This will drive number of exit signs and their locations as well as the panic hardware requirement and landing requirements. Emergency lighting needs to be provided through out. Smoke alarms need to be tested. Address numbers have been painted. Receptical covers need to be provided. See the city approved plans/review notes for items marked in red that need to be addressed.
FIR11-00095 INSP-Supply line flush8/24/20118/25/20118/25/2011 12:04:57 PMAPASS
Underground supply line flush passed.
FIR11-00159 INSP-Final Inspection8/25/20118/25/20118/25/2011 11:46:47 AMPFAIL
Forward flush passed. This project can be finaled when the tamper switches on the wet system are reporting to the central station.
MIS11-00216 FIR-Conference8/25/20118/25/20118/25/2011 11:44:15 AMPDONE
I posted a "stop work order" on site after I found two small rooms being built upstairs in the gym area.Wood framed walls, electrical work, mechanical work and fire alarm work has been performed. The mechanical work incudes ducting and a chase/soffit through the second floor exit stairway to the exterior of the building.
FIR11-00330 INSP-Supply line flush8/24/20118/25/20118/25/2011 11:38:24 AMACANC
Could not do underground flush due to United Water
FIR11-00330 INSP-Sprinkler Rough-in/Hydro8/24/20118/25/20118/25/2011 11:37:39 AMPPASS
Overhead hydro test passed.
BLD11-00101 FIRE-Final Inspection8/24/20118/25/20118/25/2011 10:44:42 AMACANC
This is a duplicate inspection that was set up for inspection performed 8/24/2011
FIR11-00095 INSP-Sprinkler Rough-in/Hydro8/24/20118/25/20118/25/2011 10:29:18 AMAPASS
The underground supply line hydro test passed.
BLD11-00859 FIRE-Final Inspection8/24/20118/25/20118/25/2011 9:03:54 AMAPASS
life safety passed.
FIR11-00427 INSP-Sprinkler Rough-in8/24/20118/25/20118/25/2011 8:50:46 AMAPASS
Sprinkler piping is ok to cover.