Inspections for the day of: Thursday, August 25, 2016.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00513 INSP-Final Inspection8/24/20168/25/20168/26/2016 9:58:30 AMAFAIL
Need NFPA 72 record of completion, need map at the FACP and need as-builts resubmitted since the provided as-builts do not match existing conditions.
BLD15-02068 FIRE-Final Inspection8/25/20168/25/20168/25/2016 2:08:13 PMPFAIL
No approved plans on site. No inspection performed.
NAF16-00034 INSP-Sprinkler Rough-in8/24/20168/25/20168/25/2016 1:43:48 PMPPASS
The underground supply piping is ok to cover.
FIR16-00554 INSP-Final Inspection8/25/20168/25/20168/25/2016 1:37:13 PMPFAIL
No approved plans on site so no inspection was performed. I went over general requirements
FIR16-00501 INSP-Final Inspection8/24/20168/25/20168/25/2016 1:37:12 PMPFAIL
No testing performed today due to agreement that additional work required for shunt trip will be added to the plans. Contractor to verify if as-builts or plan mods are acceptable.

Jordan Phone #: ###-####
BLD15-04264 FIRE-Final Inspection8/25/20168/25/20168/25/2016 12:58:26 PMPFAIL
Need fire dept access painting as discussed, need door signage as discussed and need operational permit from fire dept.

Tom Phone #: ###-####
BLD15-03008 FIRE-Final Inspection8/25/20168/25/20168/25/2016 12:20:15 PMPPASS
life safety passed
FIR16-00532 INSP-Sprinkler Rough-in8/24/20168/25/20168/25/2016 11:02:44 AMAPASS
Rough-in passed. Piping can be covered.
FIR16-00117 INSP-Final Inspection8/24/20168/25/20168/25/2016 11:02:18 AMAPASS
Permit finaled
FIR16-00107 INSP-Final Inspection8/24/20168/25/20168/25/2016 11:01:44 AMAPASS
Permit finaled