FIR15-00808
| INSP-Sprinkler Rough-in/Hydro | 8/25/2016 | 8/25/2016 | 8/25/2016 2:47:49 PM | P | DONE |
|
|
Hydrostatic test for overhead fire sprinkler piping complete.
|
FIR15-00727
| INSP-Sprinkler Rough-in | 8/25/2016 | 8/25/2016 | 8/25/2016 2:15:18 PM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping in the ballroom, sections B and C complete. Overhead fire sprinkler piping located above the grid ceiling in ballroom approved for cover.
|
FIR16-00314
| INSP-Sprinkler Rough-in/Hydro | 8/24/2016 | 8/25/2016 | 8/25/2016 12:17:50 PM | A | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 1 complete, level 1 overhead fire sprinkler piping approved for cover. Hydrostatic test for overhead fire sprinkler throughout building complete.
|
FIR16-00101
| INSP-Sprinkler Rough-in/Hydro | 8/24/2016 | 8/25/2016 | 8/25/2016 11:58:19 AM | A | FAIL |
|
|
Overhead fire sprinkler piping located in attic spaces on level 5 not approved for cover, plastic sheeting is installed over fire sprinkler piping but no insulation has been installed above piping, insulation tenting needs to installed over the fire sprinkler piping and inspected before cover of overhead fire sprinkler piping in attic spaces is approved.
|
BLD16-02360
| FIRE-Final Inspection | 8/24/2016 | 8/25/2016 | 8/25/2016 11:18:23 AM | A | PASS |
|
|
Fire sprinkler inspection complete, no fire alarm modifications, fire extinguisher is in common area with a current i nspection tag. Final life fire safety inspection passed/complete.
|
FIR16-00526
| INSP-Final Inspection | 8/25/2016 | 8/25/2016 | 8/25/2016 11:17:01 AM | P | PASS |
|
|
Final fire sprinkler inspection passed/complete
|
FIR16-00526
| INSP-Sprinkler Rough-in | 8/25/2016 | 8/25/2016 | 8/25/2016 11:16:00 AM | P | PASS |
|
|
Rough to cover inspection for overhead fire sprinkler piping located in area of work complete, overhead fire sprinkler piping in area of work approved for cover.
|
FIR16-00305
| INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 11:04:21 AM | A | PASS |
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping on levels 2, 3 and 4. Notated the city approved drawings with green highlighter overhead fire sprinkler piping approved for cover.
|
FIR16-00292
| INSP-Final Inspection | 8/22/2016 | 8/25/2016 | 8/25/2016 10:20:34 AM | A | PASS |
|
|
Final fire alarm communicator inspection passed/complete.
|
FIR15-00641
| INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 10:01:18 AM | A | PASS |
|
|
Rough to cover inspection for hardlids located on level 5 annex complete, overhead fire sprinkler piping located above hardlids approved for cover.
|
FIR16-00146
| INSP-Sprinkler Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 9:59:44 AM | A | PASS |
|
|
Rough to cover inspection for level 9and stairwells overhead fire sprinkler piping compete, overhead fire sprinkler piping located on level 9 and stairwells approved for cover.
|