Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC07-00572 Aging Inspection8/26/20098/26/20098/28/2009 10:08:21 AM DONE
looked at site, see site final
ELE09-01501 Final8/26/20098/26/20098/26/2009 3:57:15 PMPPASS
this is for final inspection. Please call me so i can let homeowner know when yu will be going. Phone #: ###-#### Internet Inspection Request from: Daniel Gamboa ok to final, no esc this project
ESC09-00232 General Inspection8/26/20098/26/20098/26/2009 3:33:32 PMPPASS
looked ok
ESC09-00349 General Inspection8/26/20098/26/20098/26/2009 3:32:45 PMPPASS
looked ok
ESC09-00303 General Inspection8/26/20098/26/20098/26/2009 3:32:00 PMPPASS
looked ok
ESC09-00305 General Inspection8/26/20098/26/20098/26/2009 3:31:26 PMPPASS
looked ok
ESC09-00335 General Inspection8/26/20098/26/20098/26/2009 3:30:10 PMPPASS
looked ok
ESC09-00523 General Inspection8/26/20098/26/20098/26/2009 3:29:24 PMPNR
too early, no signs or work started
ESC09-00467 General Inspection8/26/20098/26/20098/26/2009 3:28:31 PMPNR
too early, no signs or work started
ESC09-00468 General Inspection8/26/20098/26/20098/26/2009 3:27:42 PMPNR
too early, no signs or work started
ELE09-01227 Final8/25/20098/26/20098/26/2009 3:21:47 PMPPASS
Phone #: ###-#### Internet Inspection Request from: Stephen Kren called contractor, ok to final
ELE09-01592 Electrical Rough-In8/25/20098/26/20098/26/2009 2:37:06 PMPPASS
Phone #: ###-#### Internet Inspection Request from: Andy Derrick called contractor, ric ok
ELE09-01589 Permanent Service8/25/20098/26/20098/26/2009 12:43:24 PMPPASS
Matt is the Contact Name & # Phone #: ###-#### Internet Inspection Request from: chris green p/s o/h rec ok, check for additional ground rod at final, labelling, abrasion protection at sub-panel, no esc this project
ELE09-01291 Final8/25/20098/26/20098/26/2009 11:39:11 AMAPASS
Scheduled by a contractor via Hello! on 8/25/2009 at 3:38:40 PM. Contact: ###-####. ok to final
ELE09-01290 Final8/25/20098/26/20098/26/2009 10:37:05 AMAPASS
Scheduled by a contractor via Hello! on 8/25/2009 at 3:37:48 PM. Contact: ###-####. ok to final
ELE09-01433 Final8/25/20098/26/20098/26/2009 10:18:02 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Erick Baker ok to final, no esc this project
ELE09-01433 Electrical Rough-In8/26/20098/26/20098/26/2009 9:51:10 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Erick Baker buried conduit was exposed, depth and installation ok, ok to cover, no esc this project
ELE09-01387 Final8/25/20098/26/20098/26/2009 9:48:48 AMAPASS
bob Phone #: ###-#### ok to final, signed structural card
ELE09-01565 Temporary Service8/25/20098/26/20098/26/2009 9:15:59 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Brandon Blackham corrections made, t/s u/g n ok
ELE09-01563 Temporary Service8/25/20098/26/20098/26/2009 8:51:16 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Brandon Blackham corrections made, t/s u/g n ok
ELE09-01566 Temporary Service8/25/20098/26/20098/26/2009 8:27:58 AMAPASS
Phone #: ###-#### Internet Inspection Request from: Brandon Blackham corrections made, t/s u/g n ok
ELE09-01467 Electrical Rough-In8/25/20098/26/20098/26/2009 8:08:11 AMAPASS
final inspection on ufer ground and any questions please call Rob ###-#### Phone #: ###-#### Internet Inspection Request from: Andy Rose ok to cover gec
ELE09-01467 Permanent Service8/26/20098/26/20098/26/2009 8:08:00 AMAPASS
final inspection on ufer ground and any questions please call Rob ###-#### Phone #: ###-#### Internet Inspection Request from: Andy Rose p/s u/g n ok