FIR14-00372
| INSP-Alarm Testing | 8/26/2014 | 8/26/2014 | 8/29/2014 4:25:06 PM | P | DEFR |
|
|
Phone #: ###-#### Inspection requested via web by Keith Olstrom
|
FIR14-00071
| INSP-Sprinkler Rough-in | 8/26/2014 | 8/26/2014 | 8/29/2014 4:24:51 PM | P | PART |
|
|
UG fire supply line at building L from the meter to a point just ahead of the first 90 okayed for bury. NOTE: thrust blocking not yet installed.
|
FIR14-00601
| INSP-Sprinkler Rough-in | 8/26/2014 | 8/26/2014 | 8/26/2014 2:38:39 PM | P | PART |
|
|
Okay to cover fire sprinkler modifications at the grid ceilings.
|
FIR13-00409
| INSP-Final Inspection | 8/19/2014 | 8/26/2014 | 8/26/2014 1:42:52 PM | A | PASS |
|
|
Verified previous correction items and plan modification. Remainder of fire alarm work completed and passed inspection. Permit finaled.
|
FIR14-00600
| INSP-Sprinkler Rough-in | 8/25/2014 | 8/26/2014 | 8/26/2014 1:41:07 PM | A | PART |
|
|
Two offices as marked on plan and indicated on the scope of work are okay for cover. However, noted three additional locations in need of sprinkler coverage adjustments due to tenant remodel work-
|