Inspections for the day of: Tuesday, August 26, 2014.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00396 INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014 3:18:29 PMPFAIL
Tenting is still not complete.
BLD14-01601 FIRE-Final Inspection8/26/20148/26/20148/26/2014 2:58:52 PMPPASS
life safety passed
BLD14-01317 FIRE-Final Inspection8/26/20148/26/20148/26/2014 2:28:32 PMPPASS
Life safety passed
FIR14-00443 INSP-Sprinkler Rough-in/Hydro8/25/20148/26/20148/26/2014 2:08:59 PMPPASS
Rough-in and overhead hydro test passed. Piping can be covered.
GCB14-00058 FIRE-Final Inspection8/26/20148/26/20148/26/2014 2:08:10 PMPPASS
Life safety passed.
FIR14-00536 INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014 10:45:31 AMPPASS
Underground ok for cover
FIR14-00533 INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014 10:45:11 AMPPASS
Underground ok for cover
FIR14-00534 INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014 10:42:15 AMPPASS
Underground ok for cover
FIR14-00535 INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014 10:41:51 AMPPASS
Underground ok for cover
FIR14-00396 INSP-Sprinkler Rough-in8/26/20148/26/20148/26/2014 10:03:27 AMAFAIL
Tenting is not complete. Piping can not be covered.
FIR14-00511 INSP-Sprinkler Rough-in8/25/20148/26/20148/26/2014 9:38:20 AMAPASS
Remaining piping is ok to cover.
FIR14-00296 INSP-Final Inspection8/25/20148/26/20148/25/2014 1:58:58 PMAPASS
Permit finaled
FIR14-00337 INSP-Final Inspection8/25/20148/26/20148/25/2014 1:56:57 PMAPASS
Permit finaled