PLM03-00660
| PLM-Aging Inspection | 8/27/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | | PASS |
|
|
work still in progress 8/27/2003 8:22:49 AM
|
PLM03-02563
| Water and/or Sewer | 8/26/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | A | NR |
|
|
dennis//sewer only; Phone #: ###-#### Internet Inspection Request from: Barbara Moore not ready 8/27/2003 10:29:29 AM
|
PLM03-02661
| Plumbing Rough-in | 8/26/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | A | PASS |
|
|
ROY TOWERS; Phone #: ###-#### Internet Inspection Request from: Pam Masselli
|
PLM03-02667
| Sprinkler (Final) | 8/26/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | A | PASS |
|
|
###-#### mike
|
PLM03-02658
| Plumbing Rough-in | 8/26/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 8/26/2003 at 2:15:56 PM. Contact: ###-####.
|
PLM03-01839
| Final | 8/26/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 8/26/2003 at 4:06:35 PM. Contact: ###-####.
|
PLM03-02648
| Sprinkler (Final) | 8/26/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | A | PART |
|
|
tie in ok ok to cover need to have double check tested and certified contractor to recall when ready 8/27/2003 1:23:25 PM
|
PLM03-02206
| Groundwork | 8/27/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 8/27/2003 at 9:30:28 AM. Contact: ###-####.
|
PLM03-00288
| Plumbing Rough-in | 8/27/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | P | PART |
|
|
###-#### jason rest room on east side of building test ok 8/27/2003 5:24:15 PM
|
PLM03-02448
| Plumbing Rough-in | 8/27/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 8/27/2003 at 10:15:56 AM. Contact: ###-####.
|
PLM03-01921
| Plumbing Rough-in | 8/27/2003 | 8/27/2003 | 8/27/2003 12:00:00 AM | P | FAIL |
|
|
Phone #: ###-#### Internet Inspection Request from: Liz Sasser repipe island sink,s as per upc 909.0 need additional cleanouts in trap arm,s exceeding 90 as per upc 1002.3 need to support all piping as per table 3-2 need to correct all venting that exceed 1/3 of permitted length as per table 7-5 need to submitt plan showing all additional plumbing in operatory room,s and relocation of med gas room 8/27/2003 5:00:34 PM
|