Inspections for the day of: Thursday, August 27, 2009.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00033 INSP-Alarm Testing8/27/20098/27/20098/28/2009 5:26:35 PMPPART
Continued inspection completed 8/27 afternoon and evening by F. France and B. Johnson for the remainder project related fire alarm permit work FIR09-00296 including correction items. Room signage, building map, program changes, and breaker lock okayed, vesda faults tested okay, signals at main FACP verified, low air supervisory signals tested, alert and alarm signals sent/recieved, transport times at several systems measured and found to be under max. time limits, systems 22, 23, 24, 25 and 17 passed, system 18 failed. Continued testing while system 18 repaired. Sequence of operation passed for the freezer systems including rack systems 26,27,28,29, and area served. Repairs at system 18 modules and VESDA completed and retested okay per B. Johnson. Final pending NFPA 72 record of inspection and testing and record of completion documents for signature.
FIR09-00296 INSP-Alarm Testing8/26/20098/27/20098/28/2009 5:24:51 PMPPART
Continued inspection completed 8/27 afternoon and evening by F. France and B. Johnson for the remainder permit work including correction items. Room signage, building map, program changes, and breaker lock okayed, vesda faults tested okay, signals at main FACP verified, low air supervisory signals tested, alert and alarm signals sent/recieved, transport times at several systems measured and found to be under max. time limits, systems 22, 23, 24, 25 and 17 passed, system 18 failed. Continued testing while system 18 repaired. Sequence of operation passed for the freezer systems including rack systems 26,27,28,29, and area served. Repairs at system 18 modules and VESDA completed and retested okay per B. Johnson. Final pending NFPA 72 record of inspection and testing and record of completion documents for signature.
FIR09-00328 FIR-Aging Inspection8/27/20098/27/20098/28/2009 12:59:02 PM DONE
Pending site inspection request for work completed.
FIR09-00389 INSP-Final Inspection8/27/20098/27/20098/28/2009 12:53:46 PMPCANC
Precluded by work on FIR09-00296.
FIR09-00388 INSP-Final Inspection8/27/20098/27/20098/28/2009 12:53:24 PMPCANC
Precluded by work on FIR09-00296.
FIR09-00387 INSP-Final Inspection8/27/20098/27/20098/28/2009 12:52:53 PMPCANC
Precluded by work on FIR09-00296.
FIR09-00505 INSP-Sprinkler Rough-in8/27/20098/27/20098/28/2009 12:34:36 PMPNR
Per site visit by T. Frost dated 8/27/09, work is incomplete and not ready for inspection as requested.
FIR09-00485 INSP-Sprinkler Rough-in8/26/20098/27/20098/28/2009 12:32:06 PMAPART
Fire sprinkler system modifications for the scope of work are approved for cover per inspection completed by T. Frost, contractor was notified a hydrostatic test will be necessary due to over 20 heads affected.
FIR09-00164 INSP-Alarm Testing8/27/20098/27/20098/28/2009 12:28:43 PMPPART
Fire alarm testing is not ready at this time, contractor requested inspection type be changed to begin 24 hr. air test of the new dry sprinkler system- Test started at 3:00pm @ 43psig 8/27/09 by T. Frost.
FIR07-00515 INSP-Sprinkler Rough-in/Hydro8/26/20098/27/20098/28/2009 12:25:51 PMPPART
See inspection notes per site visit by T. Frost -Ok to cover. However, there is inadequate coverage under the outside canopy on both levels. I advised the fitter that due to the limited water supply it may be inadvisable to cover the piping until a new plan was designed for protection of the outside canopies. The pipe size may be inadequate to supply all of the sidewall sprinklers.
FIR09-00509 INSP-Final Inspection8/27/20098/27/20098/27/2009 1:02:01 PMAPASS
Fire sprinkler permit work passed both rough-in and final inspections completed at the same time, C/N items are finished.
FIR09-00508 INSP-Sprinkler Rough-in/Hydro8/27/20098/27/20098/27/2009 1:00:50 PMAPART
Overhead work per the scope of permit at the tenant remodel is good for cover at the drop ceilings.
BLD09-01406 FIRE-Final Inspection8/26/20098/27/20098/27/2009 12:59:31 PMAFAIL
Second exit door not shown on plans at the south side of the tenant space must be provided with approved hardware per IFC and IBC standards as discussed.
FIR09-00164 INSP-Sprinkler Rough-in/Hydro8/26/20098/27/20098/27/2009 12:57:23 PMAPART
Hydrostatic testing completed satisfactory for the new attic and second floor dry system.
BLD09-00302 FIRE-Final Inspection8/26/20098/27/20098/27/2009 12:55:56 PMADEFR
Permit details do not indicate any project required fire inspection signatures are applicable.
FIR09-00477 INSP-Final Inspection8/26/20098/27/20098/27/2009 12:54:26 PMAFAIL
Report at off site monitoring does not indicate correct zone, type or description of account activity for test signals sent, no alarms recieved.