Inspections for the day of: Friday, August 27, 2010.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-00373 FIRE-Sprinkler Rough-in8/27/20108/27/20108/27/2010 3:04:01 PMPPART
Okay to cover overhead fire sprinkler system modifications at the grid ceilings.
FIR10-00276 INSP-Conference8/27/20108/27/20108/27/2010 3:02:36 PMPDONE
Regarding 7:00 AM alarm inspection 9/2
FIR10-00256 INSP-Final Inspection8/26/20108/27/20108/27/2010 2:56:34 PMPPASS
Fire sprinkler permit final approved.
FIR10-00258 INSP-Final Inspection8/26/20108/27/20108/27/2010 2:56:07 PMPPASS
Fire sprinkler permit final approved.
FIR10-00305 INSP-Final Inspection8/26/20108/27/20108/27/2010 2:55:08 PMPPASS
Correction items finished, final fire alarm testing passed. Permit finaled.
BLD10-00018 FIRE-Conference8/27/20108/27/20108/27/2010 2:53:26 PMPDONE
Regarding fire life safety final and project related fire sprinkler permit work.
BLD10-01337 FIRE-Final Inspection8/27/20108/27/20108/27/2010 1:39:25 PMPNR
Tom Phone #: ###-####
BLD10-01347 FIRE-Final Inspection8/26/20108/27/20108/27/2010 10:51:31 AMAPASS
Life safety inspection passed, fire extinguisher to be posted as discussed.
BLD10-01337 FIRE-Final Inspection8/26/20108/27/20108/27/2010 10:50:21 AMANR
Project related fire alarm permit must be requested for and pass final inspection prior to building fire life safety approval. Notified contractor of the necessary steps to be completed for occupancy.
BLD10-01336 FIRE-Final Inspection8/26/20108/27/20108/27/2010 10:49:52 AMANR
Project related fire alarm permit must be requested for and pass final inspection prior to building fire life safety approval. Notified contractor of the necessary steps to be completed for occupancy.