Inspections for the day of: Thursday, August 27, 2015.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-03405 FIRE-Final Inspection8/26/20158/27/20158/27/2015 3:44:27 PMPPASS
Final fire and life satey inspection for Tower 4 portion of the building, including the east side parking garage. Tested exit signs and emergency lights for these areas. A few exit signs were added to improve locations of exits in the garage. EM lighting tested OK.
EVAC plans were installed in all units for this portion of the building. Fire extinguisers are installed. Fire sprinklers and fire alarm systems have been finaled. Areas of Refuge call systems(all elevators) were tested and all answered by lobby staff, or by monitoring company.
BLD13-00016 FIRE-Final Inspection8/27/20158/27/20158/27/2015 3:38:52 PMPPART
Preliminary walk through of JUMP structure to see changes made to egress signs, walking surfaces, etc. from last inspection. An early morning retest of the EM lighting and exit signage off the generator is scheduled for 8/28 am. Some of the exit stairs (parking garage) are not completed yet, but are scheduled to be done also by 8/28. TCO for a small group of emplyees for use of the JUMP building is being proposed next week, pending successful completion of the EM light retest.
FIR14-00875 INSP-Final Inspection8/26/20158/27/20158/27/2015 3:38:30 PMAPASS
Final inspection/test of fire alarm system for Tower 4 area - all floors, including elevator 2 recal/alt. recall functions, area SD for elevator lobbies, unit smoke detection, etc.
All devices tested satisfactorily.. System is being monitored off site - correct address was confirmed.
FIR14-00875 INSP-Final Inspection8/27/20158/27/20158/27/2015 3:32:52 PMPPASS
Final inspection/test of fire alarm system for Tower 4 - all floors, including elevator# 2 recall/alt. recall functions, SDs for elevator lobbies, unit SDs, etc. All devices tested satisfactorily. Offsite monitoring and correct address confirmed.
FIR14-00191 INSP-Final Inspection8/26/20158/27/20158/27/2015 1:54:48 PMAPASS
Final inspection and signoff for this permit.
FIR14-00430 INSP-Sprinkler Rough-in/Hydro8/26/20158/27/20158/27/2015 1:53:49 PMAPASS
Final inspection and sign off for this permit.
FIR14-00531 INSP-Final Inspection8/26/20158/27/20158/27/2015 1:53:08 PMAPASS
Final inspection and signoff for this permit.