BLD02-01179
| BLD-Framing/Rough-in | 8/27/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | A | CANC |
|
|
one hour shaft . need to complete to flutes. 8/28/2002 12:08:54 PM
|
BLD02-01794
| BLD-Framing/Rough-in | 8/27/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 08/27/2002 at 15:53:38. Contact: ###-####. need detail for slip joint contractor will get this . 8/28/2002 12:59:50 PM
|
BLD02-01675
| BLD-Final | 8/27/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | A | PASS |
|
|
###-####. Ok perm on rest rooms no card at site. 8/28/2002 12:34:25 PM
|
MEC02-02329
| Rough-in | 8/28/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/28/2002 at 07:57:08. Contact: ###-####.
|
MEC02-02329
| Rough-in | 8/28/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 08/28/2002 at 07:57:08. Contact: ###-####.
|
BLD02-01959
| BLD-Footing | 8/28/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | P | PART |
|
|
###-#### footings poured, now seting up walls. 8/28/2002 3:54:45 PM
|
BLD02-00700
| BLD-Other | 8/28/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 08/28/2002 at 08:36:42. Contact: ###-####.a-325 bolts req s-i. 8/28/2002 3:53:03 PM
|
MEC02-01734
| Final | 8/28/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 08/28/2002 at 08:57:39. Contact: ###-####.ok temp oc, c/n popsted. 8/28/2002 3:54:03 PM
|
BLD01-00873
| BLD-Final | 8/27/2002 | 8/28/2002 | 8/28/2002 12:00:00 AM | P | FAIL |
|
|
###-#### nick c/n posted. 8/28/2002 3:54:14 PM
|