Inspections for the day of: Thursday, August 28, 2008.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-01159 FIRE-Final Inspection8/28/20088/28/20088/28/2008 4:34:46 PMPFAIL
Could not complete fire life safety, Fire alarm permit needs to be finaled.KR
FIR08-00495 INSP-Final Inspection8/28/20088/28/20088/28/2008 4:33:36 PMPNR
Will call in for tomorrow.KR
FIR08-00045 INSP-Sprinkler Rough-in8/28/20088/28/20088/28/2008 3:55:41 PMPFAIL
Chris- call 30 min prior to going to meet Phone #: ###-#### No access yet provided to inspect dry uprights as noted per last site visit completed 8/19, inspection rescheduled per phone conversation.
FIR08-00018 INSP-Sprinkler Rough-in/Hydro8/28/20088/28/20088/28/2008 3:53:20 PMPFAIL
As-built plans for field modifications on the 7th floor do not match field installation as requested, marked locations where discrepancies remain, final rough-in approval will require resubmittals as previously discussed.
FIR08-00495 INSP-Final Inspection8/28/20088/28/20088/28/2008 3:34:57 PMPCANC
duplicate
FIR08-00488 INSP-Final Inspection8/28/20088/28/20088/28/2008 2:40:33 PMPCANC
Forrest, This is a new T.I. to a vanilla shell permit that wasn''t completed. I spoke to Troy (I believe) and he said to schedule this inspection with the vanilla shell inspection (FIR07-01036), and get them both signed off. Thank You. Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
FIR07-01036 INSP-Final Inspection8/28/20088/28/20088/28/2008 2:40:19 PMPCANC
Forrest, This was a vanilla shell permit that wasn''t completed. I spoke to Troy (I believe) and he said to schedule this inspection when we schedule for the T.I. inspection (FIR08-0488), and get them both signed off. Thank You. Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
FIR08-00168 INSP-Alarm Testing8/28/20088/28/20088/28/2008 2:19:39 PMPNR
Phase two building construction is not yet complete.
BLD08-00685 FIRE-Final Inspection8/28/20088/28/20088/28/2008 2:10:42 PMPDEFR
mike - fire life safety Phone #: ###-#### NOTE..........Notified contact that no fire permit related inspection or signatures are required for this project per permit details- request was intended for a structural inspection.
BLD07-01689 FIRE-Final Inspection8/28/20088/28/20088/28/2008 2:03:04 PMPPASS
Fire life safety approved per last visit-see project activities for details, related fire sprinkler and alarm permits are finaled.
FIR08-00433 INSP-Sprinkler Rough-in8/28/20088/28/20088/28/2008 2:00:02 PMPFAIL
Need to provide missing thrust block at one location.
FIR07-01022 INSP-Final Inspection8/27/20088/28/20088/28/2008 1:29:14 PMPPASS
Heat detector in frieght elevator control room was repaired and tested, per last inspection. KR
FIR08-00588 INSP-Sprinkler Rough-in8/28/20088/28/20088/28/2008 11:48:56 AMAPART
Okay for cover at the drop ceilings.
BLD07-03215 FIRE-Final Inspection8/28/20088/28/20088/28/2008 11:07:17 AMACANC
Wrong permit number request.
FIR08-00366 FIR-Aging Inspection8/28/20088/28/20088/28/2008 9:59:41 AM DONE
Pending site inspection request. WIP.
FIR08-00567 INSP-Sprinkler Rough-in8/28/20088/28/20088/28/2008 9:57:52 AMAPART
See plan annotations for locations inspected to date.
FIR08-00490 INSP-Conference8/28/20088/28/20088/28/2008 9:56:57 AMADONE
Regarding smoke detector locations