BLD08-01159
| FIRE-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 4:34:46 PM | P | FAIL |
|
|
Could not complete fire life safety, Fire alarm permit needs to be finaled.KR
|
FIR08-00495
| INSP-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 4:33:36 PM | P | NR |
|
|
Will call in for tomorrow.KR
|
FIR08-00045
| INSP-Sprinkler Rough-in | 8/28/2008 | 8/28/2008 | 8/28/2008 3:55:41 PM | P | FAIL |
|
|
Chris- call 30 min prior to going to meet Phone #: ###-#### No access yet provided to inspect dry uprights as noted per last site visit completed 8/19, inspection rescheduled per phone conversation.
|
FIR08-00018
| INSP-Sprinkler Rough-in/Hydro | 8/28/2008 | 8/28/2008 | 8/28/2008 3:53:20 PM | P | FAIL |
|
|
As-built plans for field modifications on the 7th floor do not match field installation as requested, marked locations where discrepancies remain, final rough-in approval will require resubmittals as previously discussed.
|
FIR08-00495
| INSP-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 3:34:57 PM | P | CANC |
|
|
duplicate
|
FIR08-00488
| INSP-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 2:40:33 PM | P | CANC |
|
|
Forrest, This is a new T.I. to a vanilla shell permit that wasn''t completed. I spoke to Troy (I believe) and he said to schedule this inspection with the vanilla shell inspection (FIR07-01036), and get them both signed off. Thank You. Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
|
FIR07-01036
| INSP-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 2:40:19 PM | P | CANC |
|
|
Forrest, This was a vanilla shell permit that wasn''t completed. I spoke to Troy (I believe) and he said to schedule this inspection when we schedule for the T.I. inspection (FIR08-0488), and get them both signed off. Thank You. Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
|
FIR08-00168
| INSP-Alarm Testing | 8/28/2008 | 8/28/2008 | 8/28/2008 2:19:39 PM | P | NR |
|
|
Phase two building construction is not yet complete.
|
BLD08-00685
| FIRE-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 2:10:42 PM | P | DEFR |
|
|
mike - fire life safety Phone #: ###-#### NOTE..........Notified contact that no fire permit related inspection or signatures are required for this project per permit details- request was intended for a structural inspection.
|
BLD07-01689
| FIRE-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 2:03:04 PM | P | PASS |
|
|
Fire life safety approved per last visit-see project activities for details, related fire sprinkler and alarm permits are finaled.
|
FIR08-00433
| INSP-Sprinkler Rough-in | 8/28/2008 | 8/28/2008 | 8/28/2008 2:00:02 PM | P | FAIL |
|
|
Need to provide missing thrust block at one location.
|
FIR07-01022
| INSP-Final Inspection | 8/27/2008 | 8/28/2008 | 8/28/2008 1:29:14 PM | P | PASS |
|
|
Heat detector in frieght elevator control room was repaired and tested, per last inspection. KR
|
FIR08-00588
| INSP-Sprinkler Rough-in | 8/28/2008 | 8/28/2008 | 8/28/2008 11:48:56 AM | A | PART |
|
|
Okay for cover at the drop ceilings.
|
BLD07-03215
| FIRE-Final Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 11:07:17 AM | A | CANC |
|
|
Wrong permit number request.
|
FIR08-00366
| FIR-Aging Inspection | 8/28/2008 | 8/28/2008 | 8/28/2008 9:59:41 AM | | DONE |
|
|
Pending site inspection request. WIP.
|
FIR08-00567
| INSP-Sprinkler Rough-in | 8/28/2008 | 8/28/2008 | 8/28/2008 9:57:52 AM | A | PART |
|
|
See plan annotations for locations inspected to date.
|
FIR08-00490
| INSP-Conference | 8/28/2008 | 8/28/2008 | 8/28/2008 9:56:57 AM | A | DONE |
|
|
Regarding smoke detector locations
|