BLD12-01793
| BLD-Wall Bracing | 8/28/2012 | 8/28/2012 | 8/28/2012 5:19:37 PM | P | PASS |
|
|
ok to cover ext
|
BLD12-01793
| BLD-Framing/Rough-in | 8/27/2012 | 8/28/2012 | 8/28/2012 5:19:16 PM | P | CANC |
|
|
Shear inspecrion please-Joe Phone #: ###-#### shear ok to cover ext
|
BLD12-02041
| BLD-Framing/Rough-in | 8/27/2012 | 8/28/2012 | 8/28/2012 5:18:22 PM | P | PASS |
|
|
John Phone #: ###-####
|
BLD12-01173
| BLD-Footing | 8/28/2012 | 8/28/2012 | 8/28/2012 2:14:34 PM | P | NR |
|
|
Anton-Around 3:30 if possible please Phone #: ###-####
|
BLD12-00990
| BLD-Wall Bracing | 8/28/2012 | 8/28/2012 | 8/28/2012 1:58:56 PM | P | PASS |
|
|
joe Phone #: ###-####
|
BLD11-02760
| BLD-Energy code compliance | 8/28/2012 | 8/28/2012 | 8/28/2012 1:57:08 PM | P | PASS |
|
|
please call 10 minutes prior for meeting - pamela Phone #: ###-####
|
BLD12-02032
| BLD-Framing/Rough-in | 8/27/2012 | 8/28/2012 | 8/28/2012 12:06:08 PM | A | PASS |
|
|
Please call 20min prior for access - Jim Phone #: ###-####
|
BLD12-00999
| BLD-Other | 8/27/2012 | 8/28/2012 | 8/28/2012 12:05:52 PM | A | PART |
|
|
1st Lift Masonry (High Lift) Elevator Shaft (Grout @ 9AM) Phone #: ###-#### >> Inspection requested via web by ryan steinwand crew still needs to place rebar mti will do spec inspection final sign off befor grouting
|
ESC12-00122
| Site Final | 8/28/2012 | 8/28/2012 | 8/28/2012 12:04:32 PM | A | PASS |
|
|
|
ESC12-00122
| DOC - Permit Finaled | 8/28/2012 | 8/28/2012 | 8/28/2012 12:04:23 PM | P | PASS |
|
|
|
BLD12-00297
| BLD-Final | 8/27/2012 | 8/28/2012 | 8/28/2012 12:04:09 PM | A | PASS |
|
|
Clint Phone #: ###-####
|
BLD12-00297
| DOC - Permit Finaled | 8/28/2012 | 8/28/2012 | 8/28/2012 12:04:00 PM | P | PASS |
|
|
|
BLD12-01103
| BLD-Framing/Rough-in | 8/27/2012 | 8/28/2012 | 8/28/2012 9:27:47 AM | A | PART |
|
|
grid inspection. Job trailer is located on the west side by the loading dock. Please call when on site. Phone #: ###-#### >> Inspection requested via web by alan fontenot Ceiling grid over deli area the old construction the grid is tied off to 6inch metal studs on 6ft centers becouse roof is 20 ft up this this type of construction is ok as long as studs are 18 gage or better and grid mains are wired at 4 c/c and all fixture have wires.
|
BLD12-01455
| BLD-Other | 8/27/2012 | 8/28/2012 | 8/28/2012 9:21:55 AM | A | PASS |
|
|
epoxy anchor bolt insp//Mike Phone #: ###-####
|
BLD12-02196
| BLD-Footing | 8/27/2012 | 8/28/2012 | 8/28/2012 9:21:39 AM | A | PASS |
|
|
Late am please--Eric Phone #: ###-####
|