Inspections for the day of: Thursday, August 29, 1996.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAlan Hauser
TitleMEC-COM/RES INSPECTOR
Phone #794-9453
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC96-01853 INSP - Final8/29/19968/29/19968/29/1996 12:00:00 AM CANC
/ / 350 - DONE #327
MEC96-01853 INSP - Final8/29/19968/29/19968/29/1996 12:00:00 AM CANC
/ / 350 - DONE #327
MEC96-02398 INSP - Gas log/ Fireplace8/29/19968/29/19968/29/1996 12:00:00 AM PASS
/ / 350 - F/P OK FINAL
BLD96-00596 INSP - Letter of compliance8/29/19968/29/19968/29/1996 12:00:00 AM PASS
/ / 350 - C/C#11630
BLD96-00596 INSP - Final8/29/19968/29/19968/29/1996 12:00:00 AM PASS
/ / 350 - FINAL
BLD96-00596 INSP - Letter of compliance8/29/19968/29/19968/29/1996 12:00:00 AM PASS
/ / 350 - C/C#11630
MEC96-02477 INSP - Rough-in & Gas Pressure8/29/19968/29/19968/29/1996 12:00:00 AM PASS
08/29/96 350 - basic 4 R/I OK P/T OK
MEC96-02445 INSP - Framing/ Rough-in8/28/19968/29/19968/29/1996 12:00:00 AMAPASS
08/29/96 350 - IT'S A DUPLEX AND THEY WANT IT ON THE COMPLETE BUILDING R/I OK
MEC96-02446 INSP - Framing/ Rough-in8/28/19968/29/19968/29/1996 12:00:00 AMAPASS
08/29/96 350 - FRED VINCEN WILL SHOW YOU WHICH HALF OF THE DUPLEX NEEDS R/I OK
MEC96-02469 INSP - Gas pressure test8/28/19968/29/19968/29/1996 12:00:00 AMAPASS
08/29/96 350 - pressure TEST OK ON GASLINE TO EQUIP. UNDER HOOD #32914
MEC96-02116 INSP - Final8/28/19968/29/19968/29/1996 12:00:00 AMAFAIL
08/29/96 350 - NO FINAL CORRECTIONS SEAL EXHAUST DUCT INSIDE CABINET, IN AND SUPPORT GAS PIPE @ FURN. W/H
MEC96-02116 INSP - Final8/28/19968/29/19968/29/1996 12:00:00 AMAFAIL
08/29/96 350 - NO FINAL CORRECTIONS SEAL EXHAUST DUCT INSIDE CABINET, IN AND SUPPORT GAS PIPE @ FURN. W/H
MEC96-01635 INSP - Final8/28/19968/29/19968/29/1996 12:00:00 AMAPASS
08/29/96 350 - RE-INSPECTION FINAL ì
MEC96-01635 INSP - Final8/28/19968/29/19968/29/1996 12:00:00 AMAPASS
08/29/96 350 - RE-INSPECTION FINAL ì
MEC96-01772 INSP - Final8/29/19968/29/19968/29/1996 12:00:00 AMPFAIL
08/29/96 350 - STILL HAVE CORRECTIONS, NEED UPPER COMB. AIR W/H ROOM AND DRAINS ON ROOF AND FLASH AROUND R.T.U.s
MEC96-01772 INSP - Final8/29/19968/29/19968/29/1996 12:00:00 AMPFAIL
08/29/96 350 - STILL HAVE CORRECTIONS, NEED UPPER COMB. AIR W/H ROOM AND DRAINS ON ROOF AND FLASH AROUND R.T.U.s
BLD96-01968 INSP - Framing/Rough-in8/29/19968/29/19968/29/1996 12:00:00 AMPPASS
08/29/96 350 - OK TO INSULATE AFTER PLBG APPROVED I GOT THERE AHEAD OF P CORRECTIONS TO CHECK ON E.C. INSPECTION
BLD96-02177 INSP - Footings8/29/19968/29/19968/29/1996 12:00:00 AMPPASS
08/29/96 350 - FORMS READY WORKING ON REBAR, CALLS FOR 1 BAR IN FOOTINGS WALL AS PER ENGINEER STAKED OUT BY ENG. SET BACK OK
MEC96-02480 INSP - Gas pressure test8/29/19968/29/19968/29/1996 12:00:00 AMPPASS
08/29/96 350 - P/T OK #32932 GAS METER RELOCATION
MEC96-02486 INSP - Gas log/ Fireplace8/29/19968/29/19968/29/1996 12:00:00 AMPNH
08/29/96 350 - NO ONE HOME LEFT NOTICE FOR INSPECTION TIME AND NEED GAS
PLM96-02539 INSP - Plumbing Rough-in8/29/19968/29/19968/29/1996 12:00:00 AMP
late pm