FIR01-00387
| INSP-Supply line flush | 8/28/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | A | PART |
|
|
OK to cover supply line. Still need to pour thrust block at riser 8/29/2001 10:21:28 AM
|
BLD01-01488
| FIRE-Final Inspection | 8/28/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | A | PASS |
|
|
Final OKi for certificate of completion 8/29/2001 11:28:19 AM
|
BLD01-00739
| FIRE-Final Inspection | 8/28/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | A | NR |
|
|
Final Not ready. Work not completed 8/29/2001 10:58:06 AM
|
FIR01-00275
| INSP-Final Inspection | 8/28/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | P | FAIL |
|
|
REinsp Fail Supr one detector. Map of AHU locations 8/29/2001 4:40:02 PM
|
BLD01-01651
| FIRE-Final Inspection | 8/28/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | P | PASS |
|
|
Reinsp OK for permanant occupancy 8/29/2001 11:30:19 AM
|
BLD00-03691
| FIRE-Final Inspection | 8/29/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | P | PART |
|
|
###-#### OK on Fire alarm test FIR00-00112 8/29/2001 3:31:39 PM
|
BLD01-00588
| FIRE-Final Inspection | 8/29/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | P | FAIL |
|
|
Reinsp Fail C/N issued 8/29/2001 2:07:39 PM
|
FIR01-00276
| INSP-Sprinkler Rough-in/Hydro | 8/29/2001 | 8/29/2001 | 8/29/2001 12:00:00 AM | P | PART |
|
|
Added by Inspector: 406 On 8/29/2001 4:57:52 PM Spklr rough was done 6/19/01 and was OK
|