ELE12-00137
| ELE-Aging Inspection | 8/29/2013 | 8/29/2013 | 8/29/2013 3:16:21 PM | | DONE |
|
|
contractor will schedule final inspection for week of 9/02 thur 9/06
|
ELE13-02132
| Permanent Service | 8/29/2013 | 8/29/2013 | 8/29/2013 3:00:14 PM | P | PASS |
|
|
todd Phone #: ###-#### p/s u/g n ok
|
ELE13-00498
| Final | 8/28/2013 | 8/29/2013 | 8/29/2013 2:01:31 PM | P | PASS |
|
|
Contact: Andy Eckhart Phone #: ###-#### >> Inspection requested via web by Deb Gooden job complete, final ok
|
ELE13-01658
| Electrical Rough-In | 8/29/2013 | 8/29/2013 | 8/29/2013 1:03:16 PM | P | PASS |
|
|
R/I Ceiling on classroom A -- Brandon Phone #: ###-#### rough-in ok cover
|
ELE13-02318
| Final | 8/29/2013 | 8/29/2013 | 8/29/2013 12:36:42 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by steve ragan job complete, final ok
|
MIS13-00253
| ELE-Conference | 8/28/2013 | 8/29/2013 | 8/29/2013 12:09:44 PM | A | DONE |
|
|
after 8:45//call 1/2 hr prior// Lisa ###-#### Work done without permits or inspections some time ago, no apparent fire hazards. electrical in need of general maintenance
|
ELE12-02735
| Electrical Rough-In | 8/29/2013 | 8/29/2013 | 8/29/2013 11:26:25 AM | A | PASS |
|
|
rough-in ok cover ceiling grid phase 2A
|
ELE12-02735
| Final | 8/28/2013 | 8/29/2013 | 8/29/2013 11:22:47 AM | A | NR |
|
|
Ceiling final for phase 2A. Phone #: ###-#### >> Inspection requested via web by Clint Tate Not ready for final at this time.
|
ELE13-02359
| Electrical Rough-In | 8/28/2013 | 8/29/2013 | 8/29/2013 10:05:41 AM | A | PASS |
|
|
nick made corrections straps and nail plate Phone #: ###-#### >> Inspection requested via web by Robert Jangula corrction done rough-in ok cover restrooms
|
ELE13-02366
| Temporary Service | 8/28/2013 | 8/29/2013 | 8/29/2013 9:51:45 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by daniel bibikov t/s u/g n ok
|
ELE13-02349
| Permanent Service | 8/28/2013 | 8/29/2013 | 8/29/2013 9:35:48 AM | A | PASS |
|
|
Tom Phone #: ###-#### p/s u/g rec ok
|
ELE13-02036
| Final | 8/28/2013 | 8/29/2013 | 8/29/2013 9:17:46 AM | A | NR |
|
|
Phone #: ###-#### >> Inspection requested via web by Barbara Szurgot Not ready at this time
|
ELE13-02036
| Final | 8/29/2013 | 8/29/2013 | 8/29/2013 9:16:57 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Barbara Szurgot Inspection cancelled from web by: Barbara Szurgot
|
ELE13-02036
| Electrical Rough-In | 8/29/2013 | 8/29/2013 | 8/29/2013 9:15:23 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Barbara Szurgot rough-in ok cover floor heat in bath area
|
ELE13-01919
| Final | 8/28/2013 | 8/29/2013 | 8/29/2013 8:44:29 AM | A | PASS |
|
|
the access code is, 6949, thx. Phone #: ###-#### >> Inspection requested via web by Stephen Kren final ok
|
ELE13-02053
| Final | 8/28/2013 | 8/29/2013 | 8/29/2013 8:26:48 AM | A | NR |
|
|
Phone #: ###-#### >> Inspection requested via web by Nathan Fuller Not ready no signs on site
|
ELE13-02292
| Permanent Service | 8/28/2013 | 8/29/2013 | 8/29/2013 8:12:14 AM | A | PASS |
|
|
ACCESS CODE - 6417, we are wanting to get the power turned on to supply power to a couple of circuits not affected by the fire, I have a note labeled by the panel instructing that the electrician are the only ones allowed to turn on any breakers, please call me for any questions, my cell is ###-####, thanks, Terry W. Code - 6417 Phone #: ###-#### >> Inspection requested via web by Stephen Kren A/C unit will be moved today, p/s o/h rec ok
|