ELE16-00089
| Electrical Rough-In | 8/29/2016 | 8/29/2016 | 8/29/2016 2:59:18 PM | P | PASS |
|
|
Call Bob for inspection of transformers on 5th floor mezzanine. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area noted rough in ok cover
|
ELE16-00089
| Electrical Rough-In | 8/29/2016 | 8/29/2016 | 8/29/2016 2:45:25 PM | P | FAIL |
|
|
Call Bob for inspection of transformers on 5th floor mezzanine. Phone #: ###-#### Inspection requested via web by Rafael Castillo BCC 4-05-23- Unlawful to conceal. Prefunction room 453 4th floor grid installed prior to inspection. Remove tile in this area for inspection
|
ELE13-01291
| Electrical Rough-In | 8/27/2016 | 8/29/2016 | 8/29/2016 2:41:36 PM | P | PASS |
|
|
Northwest corner site underground. Call Frank Phone #: ###-#### Inspection requested via web by Brandon Robinson Area noted rough in ok cover
|
ELE16-01838
| Electrical Rough-In | 8/27/2016 | 8/29/2016 | 8/29/2016 2:09:51 PM | P | PASS |
|
|
Level 7 boardroom ceiling. Phone #: ###-#### Inspection requested via web by Brandon Robinson Area noted rough in ok cover
|
ELE16-02472
| Electrical Rough-In | 8/26/2016 | 8/29/2016 | 8/29/2016 1:38:28 PM | P | NR |
|
|
Rough In Phone #: ###-#### Inspection requested via web by Christy Cheney New service and rewire due to fire.
|
ELE16-02813
| Electrical Rough-In | 8/29/2016 | 8/29/2016 | 8/29/2016 1:23:33 PM | P | PASS |
|
|
call first ###-#### Phone #: ###-#### Inspection requested via web by PAT MILLER Basement wall dividing beds rough in ok cover
|
ELE16-01826
| Final | 8/29/2016 | 8/29/2016 | 8/29/2016 1:10:46 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Rhonda Yoast 210.8- All receptacles located with in 6' of a sink shall have GFCI protection. Utility
|
ELE16-02799
| Temporary Service | 8/26/2016 | 8/29/2016 | 8/29/2016 10:22:01 AM | A | PASS |
|
|
We will be setting the pole first thing Monday morning. If possible please inspect after 10 am. Thank you Phone #: ###-#### Inspection requested via web by Thomas Jenkins t/s o/h n ok
|
ELE16-02655
| Rough-In Permanent Service | 8/28/2016 | 8/29/2016 | 8/29/2016 10:09:27 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Emmet Bushman Wiring runs on top of wall unable to verify wiring will check on final. Rough in ok cover p/s o/h n ok
|
ELE16-02680
| Final | 8/29/2016 | 8/29/2016 | 8/29/2016 9:45:55 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Thaniel Bishop final ok
|
ELE16-01838
| Electrical Rough-In | 8/27/2016 | 8/29/2016 | 8/29/2016 9:20:36 AM | A | PASS |
|
|
Level 3 MDF UPS Panel Including UPS XFMR , UPS Unit, UPS Panel Bonding Jumper, UPS FEEDER , UPS Panel Branch Circuits. Phone #: ###-#### Inspection requested via web by Tom Betty Area noted rough in ok cover
|
ELE16-02798
| Rough-In Permanent Service | 8/29/2016 | 8/29/2016 | 8/29/2016 8:44:25 AM | A | PASS |
|
|
Phone #: ###-#### Inspection request via web by Andrea Creek gh Rough in ok cover p/s u/g n ok
|
ELE16-02797
| Final | 8/29/2016 | 8/29/2016 | 8/29/2016 8:43:01 AM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Andrea Creek Needed rough in permanent service inspection
|
ELE16-02797
| Rough-In Permanent Service | 8/29/2016 | 8/29/2016 | 8/29/2016 8:42:17 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Andrea Creek Rough in ok cover p/s u/g n ok
|