ELE17-03193
| Conference | 8/28/2018 | 8/29/2018 | 8/29/2018 2:38:31 PM | P | PASS |
|
|
Rock Hudson, Questions about a standby generator with not separately derived system connection to integrated utility service panel. Carl Phone #: ###-#### Inspection requested via web by Carl Pelletier Discussed termination points for generator hook up in Idaho Powers side
|
ELE18-02223
| Electrical Rough-In | 8/29/2018 | 8/29/2018 | 8/29/2018 2:37:20 PM | P | PASS |
|
|
This is a ceiling inspection just for rooms 105 (principal), 106 (councilor), and 107 (conf.). School is in session so please check-in thru the temporary office. The contact is Mike Fagan. Phone #: ###-#### Inspection requested via web by Richard Montgomery Ceilngs as requested ok to ocver
|
ELE18-02054
| Final | 8/28/2018 | 8/29/2018 | 8/29/2018 11:14:49 AM | A | PASS |
|
|
Key is under front mat Phone #: ###-#### Inspection requested via web by Paula Gratiot Final ok,GC will remove rod and shelve
|
ELE18-02053
| Final | 8/28/2018 | 8/29/2018 | 8/29/2018 11:14:18 AM | A | PASS |
|
|
Key under front mat Phone #: ###-#### Inspection requested via web by Paula Gratiot Final ok, GC will; remove rod above panel and shelve
|
MIS18-00328
| ELE-Conference | 8/28/2018 | 8/29/2018 | 8/29/2018 11:13:44 AM | A | DONE |
|
|
work done w/o permits No inspections until there is a permit pulled
|
ELE18-03283
| Conference | 8/28/2018 | 8/29/2018 | 8/29/2018 10:18:28 AM | A | CANC |
|
|
Need a MIS started and deliver and correction notice to homeowner on violations on pool Mis started and will post notice
|